Enter Progress of Design Object
Explanation
This activity is used to enter a design object's progress.
The progress of a design object is established when a 
milestone template and a milestone is connected to the design object, for example, 
an existing milestone with a cumulative progress value of 0% can be selected for the 
initial stage of your design object. 
A milestone template consists of one or more milestones 
and each milestone will have a pre-defined progress percentage value. These 
values are defined in design basic data. There are several methods that can be 
used to enter the progress for a design object using milestone templates and 
milestones; 
	- Define a milestone template and an initial milestone 
	for an object class. When you create a design object using this object 
	class, progress values appear automatically. For more information refer to the Assign a Milestone Template to an Object Class 
    activity description.
- As detailed in this activity, you can manually 
	enter the progress of the design object by selecting an appropriate 
	milestone template and milestone. 
- Select a design status for the milestone you 
	create, for example, you can define a progress value of 100% for the Set 
	Completed status. As a result progress values are automatically updated on 
	the design object when the Set Completed status is selected. For more 
	information refer to the activity description, Create a Milestone Template.
	
When the progress of a design object changes (i.e., a 
different milestone number is selected) the history record for this object will 
be updated. As a result, the Information Category field will receive the 
value Progress Changed. 
If a project and an activity is defined on the selected 
design object, the progress values you enter will be updated on the project 
activity. Design object progress on the activity is calculated in the same way 
as a project task. For more information refer to the Project 
Management in IFS/Asset Design about description.
Prerequisites
	- Milestone templates and milestones need 
	to be defined in design basic data.
- If a project connection already exists, the project activity needs to exist in the Released status 
	to be able to enter a progress value greater than 0%.
System Effects
If the design object is connected to a project and project activity, the progress is updated on the project activity.
Window
Design Object
Design Objects
Project 
Connections
Related Window Descriptions
Design Object
Design Objects 
Project Connections
Procedure
	- Open the Design Object,
	Design Objects or the
	Project Connections window. 
- Search for the design object for which progress should be entered. 
	Additionally, in 
	the case of the Design Object window, click the 
	Project tab.
- In the Milestone Template field, enter the milestone template to 
	be connected to the design object. Use the List of Values to select a suitable value.
- In the Milestone Number 
	field, enter the milestone number which will reflect the progress of the 
	object. Use the List of Values to select a suitable value. When you 
	select a milestone number, pre-defined values for the Cumulative Progress 
	and Cumulative Duration fields appear automatically.
- Click Save.