Create Request for Order Quotation
Explanation
This activity is used to create a request for order quotation for a design 
object, to be received by IFS/Purchasing. If the costing of equipment or 
components is not feasible in-house, a request for order quotation can be created and sent to a prospective supplier. Drawings,
sketches, and data sheets may accompany the request. This activity may also be
performed manually or using an application other than IFS Purchasing. Each 
order quotation requires the definition of Site, Latest 
Reply Date and Wanted Delivery Date. A purchase requisition is generally 
created upon the approval of the request for order quotation. 
Prerequisites
The technical requirements for the design object need to be clarified. These 
are usually connected by attaching documents.
System Effects
	- A request for order quotation, with a No Part Request line, is created. 
	
- Each separate line is also created with connections to drawings, 
	sketches and data sheets, if selected during the creation of RFQ.
Window
Design Object
Design Objects
Linear 
Design Objects
Related Window Descriptions
Design Object
Design Objects
Linear Design Objects
Procedure
	- Open the Design Object window 
	or expand a design object tree view in the Business Object 
	Explorer if you want to create a 
	request for order quotation for one object. Open the 
	Design Objects
	or Linear Design 
	Objects window 
	if you want to create a request for order 
	quotation for several objects.
- Search for the required design object(s). Select the row(s) for the design 
	object(s). 
- Right-click and click Create Request for Order Quotation. 
	The Create Request for Order
	Quotation dialog box opens up.
- In the Site field, select the site for the request 
	for order quotation.
- Optionally, in the Currency field, enter or select the code for 
	the currency in which the request for order quotation should be. 
- Optionally, in the Buyer field, enter or select the name of the 
	buyer who is responsible for the request for order quotation.
- In the Latest Reply Date field, enter or select the last day to receive 
	the quotation from the supplier(s). This must be a working day in the distribution calendar 
	specified for the site. 
- In the Wanted Delivery Date field, enter or select 
	the date when the supplier should deliver the item(s) to an 
	agreed delivery address. This can be a non working day. 
Note: The wanted delivery date entered, in the header, will be reused for all 
selected objects, by default. 
	- In the Select Information for Individual Design Objects 
	table, modify values for the Unit, Quantity and Wanted
	Delivery Date fields for an individual object in the request for 
	order quotation, if required. The value for Unit field represents the unit in 
	which the object is measured and can be modified by selecting a value on 
	clicking List. The value for Quantity field represents the requested number 
	of the object and can be modified by entering a number manually. The value 
	in the 
	Wanted Delivery Date field is as defined in the header but can be modified for an object.
	
Note: To apply the modification of a wanted delivery date for a single object to all proceeding objects click Delivery Date.
	- In the Add Documents for Selected 
	Additional Parts table, select the Add Document check box to 
	attach a document to the request for order quotation for the object. 
	Documents available are those documents that have been connected to the 
	object.
- Click OK. 
- Back on the main window, right-click, select the row for a design object 
	if applicable, and click Request for Order Quotation . The created 
	request for order quotation will be displayed.