Enter Part
Explanation
This activity is used to enter a planned requisition part line for inventory 
parts and non-inventory parts.
Prerequisites
	- An execution item must exist and be in status prior to released.
- The supplier information must have been entered in the
	Supplier window to be able to enter supplier 
	information.
- The part must have been entered as inventory or non-inventory part.
System Effects
As a result of this activity, a planned requisition part line is created. 
When the execution item is released, the information is transferred as a 
requisition line in status planned on the work order.
Window
Compatible 
Unit Navigator
Related Window Descriptions
Compatible Unit Navigator
Compatible Unit Navigator/Requisition 
Planning
Compatible Unit Navigator/Requisition 
Planning/Part
Procedure
	- Open the 
	Compatible Unit Navigator window.
- Search for an existing record.
- Select the appropriate execution item in the navigator.
- Click the Requisition Planning tab.
- Enter a new line and enter a value in the Line No, Part Site, 
	Part No, Quantity and Buy Unit 
	column.
- In the Part No field, use List of Values to select the part. 
	Primary supplier for the part is displayed in the Supplier field. You 
	can change the supplier by using List of Values.
- Enter other values as required.
- Save the information.