Add Related Sub Orders 
Explanation
Use this activity to add related contract change orders 
to one main contract change order. Connecting change orders can be relevant 
when several change orders are related to each other. E.g. a requirement for a 
change on a sales contract may cause the need to make changes to a related sub 
contract or a project. By connecting the related change orders, it is possible 
to get an overview of the total 
impact of the change. 
Cost and revenue values from the related change orders 
are displayed per cost/revenue element in the 
Impact/Financial - Total Sub Orders 
tab. A change order can only be connected as a related sub 
order to one other change order. A change order which has related change 
orders acts as a parent change order, and can in turn not be a sub order to 
another change order.  
Prerequisites
	- A contract change order should exist.
- The contract change order should not already be connected to another parent contract change order.
System Effects
	- Financial information (agreed/requested/expected cost and revenue 
	values) from the related sub orders is displayed in the 
	Impact/Financial - Total Sub Orders tab.
- The total financial impact (summarized 
	agreed/requested/expected cost and revenue values) from the related sub 
	orders is displayed in the 
	Impact/Financial - This Order tab.
Window
Contract Change Order
Related Window Descriptions
Contract Change Order/Related Sub Orders
Contract Change Order/Impact/Financial - Total Sub Orders
Contract Change Order/Impact/Financial - This Order
 
Procedure
	- Open the Contract Change Order window.
- Select the Related Sub 
	Orders tab and create a new record (F5).
- Use the List of Values in the Change 
	Order Sequence field and select or query for a Contract Change Order.
	
- Save.
- Repeated step 3 - 4 to add more related contract 
	change orders.
- Optionally, go to the 
	Impact/Financial - Total Sub Orders  
	tab to view the financial impact from all related change orders. Note the 
	summarized fields for Agreed, Requested and Expected Cost 
	and Revenues from the related sub orders.
- Optionally, go to the 
	Impact/Financial - This Order tab to view the total financial impact, both 
	from the current change order and the related sub orders. Note the 
	summarized fields for Agreed, Requested and Expected Cost 
	and Revenues for this order and the related sub orders. A value for 
	Profit and Margin is calculated if there are values in either the 
	Revenue This Order and 
	Revenue Sub Orders fields, or Cost This Order and 
	Cost Sub Orders fields.