Create Contract Change Order Forecast Lines 
Explanation
Forecast lines contain the amounts retrieved from cost/revenue elements and 
occasionally by code parts if code parts have been defined as mandatory in code 
part demands for cost elements. A contract change order forecast may consist of 
a number of lines for each cost/revenue element.  
Prerequisites
	-  Cost/revenue elements for the project should be defined in the 
	Project 
	Details/Cost Element Code Part Demand 
	tab.
-  The contract change order should exist with a status before 
	Analyzed if you want to create new forecast lines.
-  The contract change order should exist with a status before 
	Approved if you want to modify the amount on the existing forecast 
	lines.
-  The Forecast tab with its Cost and Revenue 
	tabs is only enabled if the contract change order is connected to a 
	Project ID in the contract change order header. The IFS/Project Budgeting and 
	Forecasting component should also be installed. 
System Effects
	-  The contract change order forecast line will be created. The 
	amount entered in the ETC column will also be displayed in the Unspread 
	Amount column for the created line.
-  A summary per cost revenue element (or CBS node) is added and 
	updated in Contract Change Order/Impact/Financial – This Order 
	tab.
Window
Contract Change Order
Related Window Descriptions
Contract Change Order/Forecast
Contract Change Order/Forecast/Cost
Contract Change Order/Forecast/Revenue
Procedure
Use the following procedure to add forecast lines to an existing contract 
change order forecast:
	- Open the Contract Change Order window and query for the 
	contract change order for which you want to define a contract change order 
	forecast.
- Select the Forecast tab and then the Cost or
	Revenue tab depending on whether the forecast line should be 
	entered per cost or revenue.
- Click New to create a new forecast line. 
- If applicable, use the List of Values in the Sub Project ID field 
	to select the sub project for which you want to define the forecast line. If you want to define the forecast line down to the 
	activity level use the 
	List of Values in the Activity ID field. Optionally you can use both 
	the WBS and CBS navigator to select a desired level. If you add a new 
	line then, values for what was selected in the WBS and CBS navigator will 
	automatically be entered on the new line.
- In the Cost/Revenue Element field, use the List of Values to select a cost 
	or revenue element which you want to use for the forecast.
- Optionally, in the Description field enter a description for the 
	forecast 
	line.
- In the Currency Code 
	field enter the currency code used for the forecast values if 
	multicurrency budgeting and forecasting is 
	used (defined in the Project Details/Currency tab).
- Enter a value in the ETC field
	(If multicurrency budgeting and forecasting is used 
	enter the value in either transaction, project or base B&F rate currency). 
- In the Code Parts fields, use the List of Values where applicable 
	to select required values. Note: The code parts of a cost/revenue element for 
	which it is mandatory to define values are determined on the 
	Project 
	Basic/Cost Element Code Part Demands tab or 
	Project 
	Details/Cost Element Code Part Demand tab. 
- Click Save.