Evaluate Contract Change Order
Explanation
Use this activity to evaluate the information entered on the contract change 
order (CCO). This step is an important part of analyzing the total impact of the 
change and how to further proceed with the change process. All the aspects effected 
by the change should be considered; the expected cost/revenue, risk assessment, 
resource planning, time schedules etc. 
If the change order requires external approval, this information can be 
used as the basis for replying or 
creating a proposal to be submitted to the external party. The requested values can be 
documented on the CCO by updating the Requested Cost 
or Requested Revenue in Impact/Financial 
	- This Order  tab. 
Prerequisites
	- A CCO with relevant information entered related to 
	the change should exist.
- To view the impact on cost and revenue from related sub 
	orders, the information should be defined in the  Related Sub Orders tab.  
System Effects
N/A
Window
Contract Change Order
Contract Change Orders
Related Window Descriptions
Contract Change Order
Contract Change Orders
Contract Change Order/General
Contract Change Order/Forecast
Contract Change Order/Impact
Contract Change Order/Related Sub Orders
Contract Change Order/Object Connections
Contract Change Order/Approvals
Contract Change Order/Contacts
Contract Change Order/Tasks
Contract Change Order/History
Procedure
	- Open the Contract Change Order 
	window 
	and and query for the CCO you wish to evaluate. All of the following steps 
	are optional and a guide to help you evaluate the CCO.
- Review relevant data on the General 
	tab.
- Click the 
	Related Sub Orders 
tab to see if there are any connected change orders.
- Click the 
	Impact/Financial 
	- This Order tab to view the cost or revenue for the change order. 
	You can:
		- view records with cost or revenue per cost/revenue 
		element for this order. 
- evaluate the total agreed/requested/expected cost or revenue for
		this order in the summery fields.
- evaluate the total agreed/requested/expected cost or revenue for
		the related sub orders in the summery fields.
- evaluate the 
		calculated total Profit and Margin for the change in the 
		summery fields. (Note 
		that these fields are only calculated if there are cost or revenue 
		values for both this change order and related sub orders.)
 
- Click the 
	Impact/Financial - Total Sub 
	Orders tab to view more detailed information about the cost or revenue 
	from the related sub orders.
- Click the 
	Impact/Risk tab review 
	any information describing the impact this change order will have on the 
	risk. 
- Click the Impact/Schedule 
	tab describing the impact this change order will have on the 
	schedule, e.g. if and how much the project will be delayed if this change 
	order is implemented.
- Click the Impact/Scope 
	tab to review any information describing the impact this change order will have on the scope.
	
- Click the Impact/Other 
	tab to review any information describing the impact this change order will 
	have on things like resources, other changes, other projects etc.
- When all information has been reviewed, and if the 
	change order require external approval, you can update the optional Requested 
	Cost or Requested Revenue fields and prepare the documents that 
	should be submitted to the external party.