Reject the Contract Change Order Externally 
Explanation
After information has been submitted to the relevant external approvers their 
approval or rejection in return should be recorded. Use this activity to update 
information about when and why an external contact person has rejected a 
contract change order (CCO). If any of the required external approvers have 
rejected the CCO it will be considered as 
externally rejected by the system.
Note: Information about the external rejection from each 
	contact person can be viewed in the Contract Change Order/History tab. 
 
Prerequisites
	- The CCO should have a change type that 
	requires external approval.
- A contact person who is classified as external 
	approver should be defined for at least one address in the Contract Change Order/Contacts tab.
System Effects
	- The external approval Rejected Date field in the
	Contract Change Order/General
	tab is updated when an required external approver rejects the 
	CCO. 
- The Rejected Date field in the Contract Change Order/Contacts 
	tab is also updated for the contacts who have rejected the CCO.
Window
Contract Change Order
Related Window Descriptions
Contract Change Order
Procedure
	- Open the Contract Change Order 
	window 
	and query for the CCO which 
	should be externally rejected.
- Click the Reject Externally menu option. The 
	Reject Contract Change Order - External Rejection dialog box 
	will open.
- Select the contact person who rejected the CCO in the 
	Rejected By field. Use the List of Values, to select from the 
	contacts defined in the Contract Change Order/Contacts tab.
- Select the reason for the rejection in the Reject Reason field. 
	Use the List of Values, to select from the list of pre-defined reject reasons.
- Optionally, you can change the default rejected 
	date and time in the Rejected Date field.  
- You can also enter an additional note in the Notes field if 
	required.
- Click OK to save the information.