Set Contract Change Order to Submittal Approved
Explanation
Use this activity to set a contract change order (CCO) 
to the Submittal Approved status. When the status has been set to 
Submittal Approved, it indicates that documents, proposals for cost and 
revenues etc. related to the change, are internally approved to be submitted to 
the external parties e.g. a customer or a supplier.  
Prerequisites
	- A CCO should exist in the 
	Analyzed status.
- The External Approval Required checkbox is 
	selected in the Contract Change Basic Data/Change Type tab.
- Any approval lines and approval routing steps for 
	the current status, should be approved. 
System Effects
	- The CCO is set to the Submittal Approved status.
- A history record about the status change is created 
	and displayed in the Contract Change 
	Order/History tab.
Window
Contract Change Order
Related Window Descriptions
Contract Change Order
Procedure
	- Open the Contract Change 
	Order 
	window and query for a CCO 
	in the Analyzed status.
- Right click on the header and click Status, then select the Approve before Submit 
	menu option.
- Click Yes to continue to set the CCO to Submittal Approved 
	status.