View Contract Change Order History
Explanation
Use this tab to view information about the 
contract change order (CCO) that can be used to monitor the 
development of the change order. For example it is possible to view status 
changes, when the change order was approved or the reason for rejection if externally rejected.
The Actual Date field has the date when the CCO was submitted to, or approved/rejected by the external party e.g. 
customer or supplier. The information in this tab is inserted automatically and 
effects nothing else in the system. 
History lines for the CCO are logged 
when:
	- a CCO is created.
- a CCO number is regenerated.
- at all status changes.
- a CCO is submitted. 
- a CCO is approved internally and externally.
- a CCO is rejected externally.
Prerequisites
	- A CCO should exist. 
- A general flow should be performed (e.g. statuses changes, 
	approval routings etc.) to get some history records logged.
System Effects
None.
Window
Contract 
Change Order
Related Window Descriptions
Contract Change Order/History
Procedure
	- Open the Contract Change Order
	window and query for the required CCO.
- Click the History 
	tab. 
- View the history lines. You can sort the lines in the Info Category 
	field.