Add Project Activities to Contract Line Item
Explanation
Use this activity to connect project activities to 
contract line items. Connecting activities to items serve several purposes. It makes it possible to identify 
the project activities 
which are used to execute the contract, to retrieve estimated, planned or 
baseline cost as a part of the contract estimating, and also to retrieve 
progress and accumulated cost to use as basis for doing applications for 
payment. One or several activities can be connected to a contract line 
item. 
In cases where the project activities are used to do 
estimating  the activity cost can be retrieved from the estimated, planned or baseline cost. 
This cost will then appear on the contract items for which these activities are 
connected.
 
When doing applications for payment the connected project activities 
can be used to assess the work performed to date by retrieving the progress and 
accumulated cost from the connected project activities.
Notice that the connection is for the contract and not for the contract
revision; 
so an activity connected to an item will be valid for the same item on any 
revision. Even when using applications for payments the activities connected can be 
changed at any time. The connection is for information purposes only and is used 
as a tool to value the item progress on the applications, by looking at the 
activity progress.
Prerequisites
  - Only activities that belong to projects connected to the contract can be 
  added. 
- Only activities that have not already been connected to a line item within 
  that contract can be added.
- Only activities belonging to the same project as entered in the  Project 
  ID field on the contract revision line item can be connected to the line 
  item. If a project ID is not associated with the contract line item, you
    cannot connect it to an activity. 
- Activities can be connected to, and disconnected from, contract line items 
	as long as the contract is not in status Cancelled, Closed, or 
	Lost.
System Effects
  - One or more activities will be connected to an item. 
	
- It will be possible to retrieve estimated, planned or baseline cost from 
  the connected activities and use this to set the cost value of an item.
- It will be possible to retrieve cost and progress from the connected 
	activities and use this to set the amount that you want to apply for payment 
	for.  
Window
Sales Contract
Related Window Descriptions
Sales 
Contract/Items/Activities
Sales 
Contract/Items/Lines/Items
Procedure
To add project activities on the 
Sales 
Contract/Items/Activities  tab
 follow these steps
  - Enter a new line.
- Enter the line number and the item number for the item you wish to connect 
  to an activity.
- Enter the activity sequence for the activity you want to connect to the 
  item. Use the List of Values to select from all the activities for projects registered
    on 
  the 
	Sales Contract/Project 
  tab, and are not already connected to an item. 
 Values in all the other fields will appear automatically when the activity sequence 
  is entered.
- Optionally enter a preferred 
	value in the Weighting 
	column. (The default value is 1).
- Save the information.
  
To add project activities from the 
Sales 
Contract/Items/Lines/Items tab follow these steps
  - Select the line item to which you want to add activities.
- Right-click and then click Set Activities. 
 The Contract Items Connected to Activities 
    dialog box will be opened, and values in the Contract No, Line No and Item 
  No fields appear automatically.
- Click  New to add a new activity.
- Enter the activity sequence for the activity you want to connect to the 
  item. Use the List of Values to select from all the activities for projects registered
    on 
  the 
	Sales Contract/Project 
  tab. This list will only contain activities that aren't already connected to 
	an item.
 Values in all the other fields will appear automatically when the activity sequence 
  is entered.
- Optionally enter a preferred 
	value in the Weighting 
	column. (The default value is 1)
- Click OK to save and close the dialog box.