Modify Contract Revision Line
Explanation
Use this activity to add, modify, or delete contract 
revision lines. A contract can consist of zero or more lines, each of which can 
have zero or more items. Use the contract revision line to group contract items.
 
When modifying existing contract revisions, you can only modify the line name and line description on a contract line.
Contract revision lines can be deleted as long as the 
revision does not contain any revision line items. If a revision line should be 
deleted, all the items connected to the specific revision must be removed first. See 
the Modify Revision Line Items activity.
 
Note: When modifying or removing revision lines, if Application for Payment is 
used and applications in the Planned status exist, it is recommended to 
refresh the application for the latest contract information.
Prerequisites
To add contract revisions:
	- A contract header must exist.
- A contract must not be in the Lost, 
	Canceled, Completed, or Closed status. 
- The contract revision must not be frozen.
- The contract revision must not be in the Canceled status.
    
To modify contract revisions:
	- The contract must not be in the Completed, Closed, 
	Lost, or Canceled status. 
- The contract revision must not be frozen.
    
To delete contract revisions:
	- The contract must be in the Planned status if any line 
	items exist (or have existed). If it is in any other status, the deletion of 
	line items will be logged on the 
	Sales Contract/Deleted Items 
	tab and it will not be possible to remove the line. 
- The contract revision must not be Frozen.
 
System Effects
Contract revision lines will be added, modified, or 
deleted.
Window
Sales Contract
Related Window Descriptions
Sales Contract/Items
Procedure
	- Open the 
	Sales Contract window and 
	click the 
	Items tab.
- Select the revision to which a line is to be 
	added. By default, this will be the active revision, or if there is no active 
	revision, the most recent revision.
- Create a new record.
- Enter a line number, but if it 
	is left blank, it will be calculated automatically by finding the highest 
	line number for this contract and incrementing it by 1.
- Enter a value in the Line Name field.
- A line description can be entered, but is 
	optional.
- Save the information.
- Repeat if necessary.
- To modify a contract revision, select the revision 
	in which the line should be modified and modify the revision line as 
	required.
- Save the changes.
- To delete a revision line, select the line and 
	click Delete on the toolbar.