Calculate Cost for Single Part, One Level
Explanation
This activity can be used
to 
calculate costs for one level for an inventory part. 
Note: You cannot perform a cost calculation for cost set 1.This 
optional task is to be performed by a system administrator or equivalent person. 
When calculating costs, the costs set-up throughout the system are gathered 
and attributed to the correct part. When calculating the part costs for a cost 
set, only the level cost for the selected part is calculated.
Total level cost does 
not include accumulated component material costs. No costs for any underlying 
structure will be calculated. However, 
already calculated costs of the components one level below, will be rolled up 
for one level.
This activity can be performed through One Level Part Cost Calculation 
in Part Cost and 
Part Costs
 windows.
If by-products exist, the cost of the primary product is calculated in one of 
the following ways. Either the costs of the by-products are subtracted from the 
calculated costs to determine the cost of the primary product, or the cost of 
the primary product is determined using by-product cost distribution. If you use 
by-product cost distribution, then the by-product cost distribution factors for 
each of the by-products identify how much of the calculated costs are 
subtracted. The remaining costs are used for the cost of the primary product.
If material 
overheads are defined in part overheads, the
material 
overhead is added to to the parent level in the cost structure. When material 
and general overheads are connected to a part, and the part cost record has a 
template which consists of a cost bucket that is connected to a cost element 
which uses cost element source 501 or 502, during cost calculations for a site 
or part or cost set, the system fetches costs using different overhead units as 
follows:
	- Percentage of part cost - Same as for the 
	cost element 500 (total cost). When it comes to general overhead, the rate 
	has to be applied to the part cost excluding the earlier applied general 
	overheads.
- Fixed value per unit - Add that cost to 
	part cost structure.
- Fixed value per Order/Batch - If the 
	overhead type is Material Overhead, 
	then the parent lot size is used. If parent standard size is 0, then count 
	with order size 1. To calculate unit cost, divide the fixed value with 
	parent standard order size.
- Fixed value per weight unit - The net 
	weight of the inventory part must be considered. Multiply the entered cost 
	with the net weight of the part and add that cost to the part cost 
	structure.
Prerequisites
This activity has the following prerequisites:
  - Cost sets must have been defined.
- Inventory parts must have been created.
- The cost set for which you are performing the calculation must have the 
	costs defined.
- If by-product cost distribution is used, a structure with at least one 
	by-product must exist.
- Calculation of costs using the by-product cost distribution will require 
	that the by-product cost distribution basic data has been entered for the 
	manufacturing structure using the 
	Product Structure, 
	
	Recipe Structure, or 
	Configuration Structure window. 
  
System Effects
As a result of this activity:
  - Costs will be calculated for a single part at one level, and the results 
	will be saved in the selected cost set for update and comparison purposes. 
  
- Only the level cost for the selected part will be calculated. Costs for an 
	underlying structure will not be rolled up.
- If by-product cost distribution is used, the cost will be determined for 
	the primary product by subtracting the costs distributed among the 
	by-products. Otherwise, the costs of the by-products, if any, will be 
	subtracted.   
  
- If the Copy Estimated Material Cost from 
	Inventory Part check box is selected, estimated material cost in 
	inventory part will be taken as the estimated material cost for the part for 
	the cost set and will be copied in to the field Cost Set Estimated 
	Material Cost.
 
Window
One Level Part Cost Calculation
Part Cost
Part Costs
Related Window Descriptions
One Level Part Cost Calculation 
Part Cost
Part Costs
Procedure
To perform this activity in the 
One Level Part Cost Calculation 
window, follow these steps: 
  - Open the One Level Part Cost Calculation 
    window.
- In the Site field, click List and select the site for which 
	you want to perform the cost calculation.
- In the Part No field, click List and select the part for 
	which the calculation should be performed. 
- In the Cost Set field, click List and select the cost set 
	for which you want to perform the cost calculation.
- To include the alternative of structure and routing, click List in 
	the
	Struct. Alt. and Rout. Alt. fields and select the 
	alternatives.
- In the Stop Roll list, click either Not Stop Cost Rollup 
    or 
	Stop Cost Rollup.
- If serial numbers are used, click List in the Effective Serial 
	No field and select the serial part for which the calculation should be 
	performed. If serial numbers are not used, you can specify the date on which 
	the structure and routing should be valid in the
    Effective Date field.
- Click OK. 
  
To perform this activity in the 
Part Cost  or 
Part Costs
 window, follow these steps: 
  - Open the Part Cost  or 
	Part Costs
    window.
- Select the part for which you want to perform the cost calculation.
- Right-click and then click Cost Calculations/One 
	Level Part Cost Calculation. The values from the selected part will be shown in the 
	One Level Part Cost Calculation  dialog box.
- Click OK.