Copy Costs to Cost Set One
Explanation
This activity is used to copy costs to cost set 1. This mandatory task is to be
performed by a system administrator or an equivalent person. 
Cost set 1 is used as the standard cost set. You can copy costs from any cost
set into cost set 1. If the IFS site is defined using standard costs, then
cost set 1 can only be updated by performing this activity. Since costs of cost set 1 cannot be overwritten, the current costs are moved to a history table, where they can be viewed for historical purposes. 
One of the most common mistakes you make when using IFS/Costing is that you forget to copy work center, labor, and/or subcontracting costs to a new cost set, which in this case is cost set 1. You can easily avoid this mistake by clicking 
Controls on the Copy Costs to Cost Set One  dialog box and then selecting the Copy Work Center and Labor Class Costs check box and the 
Copy Subcontracting Costs check box.
Note: If you select the Copy Work 
Center and Labor Class Costs check box, all costs for work centers and labor classes 
in the site are copied from the selected cost set to cost set 1. Similarly 
if you select the Copy Subcontracting Costs check box, all subcontracting costs for 
outside operations are copied from the selected cost set to cost set 1. In order to copy the subcontracting costs, the cost of the subcontracted part needs to be entered in the  
Subcontracting Cost window.
There are several ways to quickly copy a part:
- You can set the part status of obsolete top parts with zero on-hand to Inactive (in the 
Inventory Part window), and then order a copy of 
active parts only. The Part Status field in the Copy Costs to Cost Set One  dialog box can be used for this purpose. 
 
 Part Cost Group has a higher ranking compared to the Part Status.
 If the Part Cost Group is specified, then the system does not give consideration to the end items (top parts) .
 If only the Part Status is specified, then the system will just filter out the end items (top parts) to start with and if the 
Include Components check box is not selected, it will only copy the end items that fulfill the part status criteria. This might result in an unnecessary difference in shop order costing.
 
 
- You can do an incremental copy by clicking Controls on the 
Copy Costs to Cost Set One  dialog box and then selecting the Incremental Copy 
check box . This includes only parts that fulfill the following criterion: Total Cost in 
Cost Set From<> Total Cost in Cost Set 1. This can significantly speed up the copy process.
 
 If the Incremental Copy check box is selected, then the system always uses 
include components.
 
- You can copy cost source information if the Capture Cost Source check box is selected by clicking 
Controls on the Copy Costs 
to Cost Set One  
dialog 
box. Cost source information is used in the actual costing method and if each part has cost source information, the cost source information of the relevant part is used in transactions only if it is copied to cost set 1.
 
 If the inventory valuation method is standard cost and the cost level is per part, cost sources will not be taken into consideration or displayed on the cost detail lines.
Note: Only costs connected to structure/routing
alternative "*" are copied (due to the fact that the inventory valuation logic
only handles "*"). When you copy part costs to cost set 1 (standard costs), the
inventory is revalued, and new postings are created.
For supplier delivery overheads defined in the source 
cost set, in order to copy supplier delivery overhead into the destination cost set, 
it is required to have the Copy Supplier Delivery Overhead check box 
selected.
This activity can be performed in the Copy Costs 
to Cost Set One 
dialog box as well as Part Cost and 
Part Costs
windows.
Prerequisites
This activity has the following prerequisites:
  - Costs for a cost set other than cost set 1 must exist.
- Cost sets must be defined.
- Sites must be defined.
System Effects
As a result of this activity:
  - The inventory value will be modified for parts with inventory valuation
    method set to Standard Cost and inventory part cost level set to Cost
    Per Part. If the inventory part has
    a balance on hand, the system automatically recalculates the inventory value
    for the part. Posting types M8
	and 
	M9
	are affected, and the inventory value
    is increased or decreased accordingly.
- Postings to the accounting systems will be created, since the inventory value is
updated.
- The costs of cost set 1 cannot be overwritten, so the current costs will be moved to
a history table. This part cost history can be used to follow up on valid costs
    throughout history.
- An entry is added to the 
	Part Cost History window.
- The cost set estimated material cost of cost set 1 
	for all parts subjected to copying will be replaced with the costs of source 
	cost 
	set.
- Copying costs to 
	cost set 1 will be the only available option to update 
	cost set estimated material cost in cost set 1.
- If the Update Estimated Material Cost in 
	Inventory Part check box is selected, the estimated material cost of the 
	respective 
	inventory part is updated. 
- The part specific general overheads, material 
	overheads, sales overheads, purchase part delivery overheads and supplier 
	for purchase part delivery overheads defined for the source cost set will be 
	copied in to cost set 1. As a result, corresponding overhead records for the 
	cost set 1 will be created and could be seen in respective clients for such 
	part connected overheads. 
- For supplier delivery overheads, costs will be 
	copied to cost set 1 only if the Copy Supplier Delivery Overhead 
	check box is selected.
Window
Copy Costs to Cost Set One
Part Cost
Part Costs
Related Window Descriptions
Copy Costs to Cost Set One
Controls for Copy Costs to Cost Set One
Part Cost
Part Costs
Procedure
To perform this activity in the Copy Costs 
to Cost Set One 
dialog 
box:
  - Open the Copy Costs 
to Cost Set One 
	
	dialog box.
- To change the default site, click  List in the Site field and
    select the site whose costs you wish to copy.
- In the Cost Set field, click List and select the cost set
    whose costs you wish to copy.
- To copy only parts that belong to a particular status, enter the part status in the 
	Part Status field.
- To copy costs for a specific part, click List in the Part No field and select the part.
- To copy costs for a group of parts, click  List in the Cost
    Group field and select the cost group.
- Click Controls. The Controls for Copy Costs to Cost Set One dialog box opens.
- Select the required check boxes based on the controls you need to enable 
	and click OK.
 
	- To update the estimated material cost of inventory parts, select the Update Estimated Material Cost in Inventory Part 
	check box.
- To copy costs for parts in the underlying structure, select the Include Components check box.
- To copy costs for configurable parts, select the 
	Include Configurable Parts check box.
- To copy only those parts whose costs have been approved, select the Only Copy Approved Parts check box.
- To copy only those parts that have a new total cost since the last copy 
	operation, select the Incremental Copy check box.
- To copy work center costs and labor costs, select the 
	Copy Work Center 
	and Labor Class 
	Costs 
	check box.
- To copy subcontracting costs, select the 
	Copy Subcontracting Costs 
	check box.
- To copy supplier delivery overheads, select the 
	Copy Supplier 
	Delivery Overhead check box.
- To copy cost sources, select the Capture Cost Sources check box.
 
- Click OK on the Copy Costs to Cost Set One dialog box.
 
To perform this activity from the 
Part Cost or  
Part Costs window: 
  - Open the Part Cost or  
	Part Costs
    window.
- Query for the part and cost set whose costs you wish to copy.
- Right-click 
	on the header and then click Copy Costs To Cost Set One. The 
	Copy Costs 
to Cost Set One dialog box opens.
- Make sure that the relevant values for the particular part is available in 
	the
	Part No, Site and Cost Set fields.
- Follow the steps 5 onwards listed above.