Report Progress on Document Package
Explanation
Use this activity to report a document package's progress.
Prerequisites
	- The document package must exist.
- Each 
	document connected to the package should have the document class, document 
	number, document sheet and revision level specified. 
System Effects
  - The new progress is calculated. 
- The next time the connected activity in IFS Project is refreshed, the new 
  progress is reported to the activity. 
Window
Document Package
Related Window Descriptions
Document Package
Procedure
  - Open the 
	Document Package window and select the
    package.  
- Select the milestone reached in the Document Milestone No field for 
  each document in the package. 
- Click Save.