Connect Requirement Activity
Explanation
When a part is connected to a requirement activity, the activity dates
are used to determine need dates for material when running the right mouse 
button menu option Calculate Gross Requirement
in 
Project Product/Demand/MPL tab.
Prerequisites
  - The project item must exist.
- The requirement activity must exist.
- There cannot be a project item on a higher level in the structure that overrides the
    project cost.
System Effects
  - The activity dates are used to determine need dates for material when calculating gross
    requirement.
- An entry is made in the project item's journal.
Window
Project
Product/Items
Project Item Navigator
Related Window Descriptions
Project Product/Items
Project Item Navigator/General
Procedure
  - Select the part you want to connect to the activity.
- Use the List of Values to enter a requirement activity in the Activity Sequence field.
- Save.