Verify Resource Availability
Explanation
This activity is used to verify the resource availability for the defined 
work scope. For maintenance orders which are distributed and followed up in 
IFS/Work Order Management, employees can be searched for and allocated to the 
operations planned on a work order. For maintenance orders which are distributed 
as simplified work orders, allocating resources will be a manual process but the 
resource demand can be viewed.
Prerequisites
To perform this activity, a maintenance order must have been created and 
released.
System Effects
	- The resource availability for the defined work scope can be verified if 
	the maintenance order is distributed and followed up in IFS/Work Order 
	Management. Employees can also be allocated to the operations on a work 
	order.
- If the maintenance order is distributed with the Simplified Work 
	Order distribution type, verification of resource availability will be a 
	manual process.
Window
Maintenance Order
Prepare Work Order
Work 
Order Execution Logic
Related Window Descriptions
Maintenance Order 
Maintenance Order/Maint. Order Str. 
Maintenance Order/Maint. Order Str./Demand Roll Up
Maintenance Order/Maint. Order 
Str./Demand Roll Up/Resources 
Maintenance Order/Exec. Logic/Demand 
Roll Up 
Maintenance Order/Exec. 
Logic/Demand Roll Up/Resources
Prepare Work Order 
Prepare Work Order/Operations
Work Order Execution Logic
Work Order 
Execution Logic/Operations
Allocate Employees
Procedure
Follow this procedure to view resource demand on a maintenance order. Be 
aware that verifying if resources are available is a manual process when working 
with maintenance orders distributed as simplified work orders.
	- Open the Maintenance Order window 
	and query (F3) for the necessary maintenance order.
- Depending on your requirements you can either 
	click the Maint Order Str. tab or the 
	Exec. Logic 
	tab.
- In the relevant graphical object structure, select 
	the structure node for which demand information is to be displayed.
- Click the Demand Roll Up tab. 
	
- In the Period Type list, select the period 
	type by which data is to be aggregated. 
- Click the Resources tab and 
	view or analyze the resource demand.
Follow this procedure to allocate employees to the operations planned on a 
work order:
	- Open the 
	Prepare Work Order window and query 
	(F3) for the necessary work order. This activity can also be performed in 
	the Work Order Execution Logic window.
- Click the Operations tab.
- Right-click on the operation line and then click
	Allocate Employees. The Allocate Employees window
      opens. The fields on the window will be populated based on the information 
	entered on the operation line.
- Enter additional details or change the existing 
	ones according to your requirement. Use the List of Values where applicable.
- Select the Exclude Schedule check box if the
    employee is considered to be available twenty four hours a day. 
- Clear the Include Sub Craft check box if 
	you want to exclude the sub crafts (if applicable) in the search. Note: 
	The Include Sub Craft is selected by default if the craft contains a 
	structure.
- Select the Show All check box if you want 
	to view all the employees who fulfill the search criteria regardless of their 
	availability.
- Click Search. 
- Click the
	Allocate Employees/Results 
	tab and select the Allocate check box against the employees that 
	should be allocated to the operation (alternatively you can select multiple 
	rows, right-click and then click Allocate).
- Click OK.