Handle Status and Revision for Linear Asset
Explanation
This activity is used to manage the status and revision handling of a linear 
asset. 
The following actions are used to change the operational status:
	- Set Planned for Operation
- Set In Operation
- Set Out of Operation
- Set Scrapped
If IFS/Asset Design is installed and a design object is connected to the 
linear asset, the following actions are used to change the design status and 
hence the revision of a linear asset:
	- Set Completed
- Set ReDesign
Refer to About Linear Asset for a complete description of statuses.
Prerequisites
	- A linear asset must exist. 
- For revision handling IFS/Asset Design must be installed.
System Effects
Changing the operational status may cause the status of connected segments to 
change, if chosen to do so. It is also possible to change status on individual 
segments and that may cause the operational status on the linear asset to 
change.
Changing the design status to ReDesign, a new revision of 
	the linear asset will be created.
Window
Linear 
Asset
Design 
Object
Related Window Descriptions
Linear Asset
Design Object
Procedure
Use the following procedure to change the operational status:
	- Open the Linear Asset window and query 
	for the relevant record.
- Right click and choose the option Operational Status and then 
	click the required status change.
Use the following procedure to change the design status and hence the 
revision:
	- Open the Linear Asset window and query 
	for the relevant record.
- Right click and choose the option Design Status and then click 
	the required status change.
- By choosing the option ReDesign a new revision of the linear 
	asset will be created.
Alternative way:
	- Open the Design Object window and query 
	for the relevant record.
- Right click and choose the option Status and then click 
	the required status change.
- By choosing the option ReDesign a new revision of the connected linear 