Lead Time Calculation
Explanation
Use this activity to calculate a part’s manufacturing lead time. The 
manufacturing lead time is calculated from the default routing and lot size of 
the part. It considers the setup, move, operation times, and the efficiency 
factor entered for the operation. The total 
lead time will be reduced to reflect the operation overlapping if the overlap value 
is defined for the routing.
Prerequisites
This activity requires a part for which a routing is defined. 
System Effects
As a result of this activity:
	- The system changes the manufacturing lead-time
values on this routing alternative.
- If the routing alternative is '*', the system also updates the lead 
	times found on the 
	Inventory Part/Manufacturing tab and on the
	
	Inventory Part/Acquisition tab.
Window
Routings
Related Window Descriptions
Routings
Routings/Routings
Calculate Manufacturing Lead Time
Procedure
  - Open the Routing window and display the part by populating or by making a selective query.
- Click the 
	Routings tab. 
- Right-click and then click Calculate
    Manuf Lead Time. The 
	Lead Time Calculation 
	dialog box will be opened.
- In the Update Options list, click a suitable option. Possible 
	values are: Update, Do not Update and Update Also 
	Expected.
- Click one of the options under Capacity. The available options 
	are Average and Demonstrated. 
- Under Leadtime Calculation Basis, click a suitable option to 
	determine the lead time for the part.
- Click OK.