Connect Work Guideline to Operation
Explanation
Use this activity to connect work guidelines to a selected operation. Work guidelines
can be created manually or from a work guideline template.
Prerequisites
If a work guideline template is to be used, that template must be defined. An operation
must also be defined for a part. 
System Effects
As a result of this activity, the system connects work guidelines to an operation. When there is a standard operation as a reference, work guidelines will be connected to that operation without removing the reference.
Window
Routings
Related Window Descriptions
Routing Operation Work Guidelines
Routings
Routings/Routings
Work Guideline Template Definition
Select Work Guideline Template
Procedure
  - Query the part that has the operations to which you want to connect work guidelines.
- Click the 
	Routings  tab.
- Point to the operation to which you
    want to connect work guidelines, right-click, then click Routing Operation Work Guidelines.
- Click in the table window and create a new record (F5).
- To create a work guideline manually, enter values for the Guideline Desc
     and 
    Guideline Text  fields.
- To use a work guideline template, point to the new line, right-click, then
    click Work Guideline
    Template. Select a work guideline template, then
    click OK.
- Repeat steps 3-6 for each work guideline that you want to connect to the selected
    operation.
- Save the record (F12).