Define Material for Instruction
and Subtask
Explanation
This activity is used to define the material that will be utilized per 
instruction or subtask.
In this instance, the material can refer to necessary 
components for replacement and/or dispensable parts such as nuts and bolts. 
There can be certain materials that will not be required each time an operation 
is performed. For such occurrences, you can specify how likely it is that the 
material will be used by entering a probability percentage for the relevant 
material line. 
The parts on the material list are not connected to a 
site at this point since you may not know which workshop will perform each 
operation. You can connect the material list to a site when it is actually used 
for a maintenance task.
Prerequisites
	- An instruction or subtask needs to be defined for 
	the part revision.
- The parts that are to be included in the material 
	list must be defined as engineering parts. Similarly, the revisions for 
	these parts need to be defined as engineering part revisions. (Vehicle parts 
	are not allowed.)
- If the material is to be supplied by a particular manufacturer and/or be a specific part number from the manufacturer, 
	this manufacturer and the corresponding 
	manufacturer's part number must be entered for each part in the material 
	list.
System Effects
	- The material list for an instruction or subtask is defined.
	
- When pending maintenance tasks are distributed to 
	a work order, the material lists for these tasks will be copied and 
	connected to the work order.
Window
Instruction
Instructions per 
Maintenance Code 
Subtask
Modification 
Details 
Condition 
Monitoring Program 
Instructions 
per Fault Function 
Serial Part Revision
Post 
Maintenance Check Definition
Related Window Descriptions
Instruction 
 Instruction/Material List
Instructions per Maintenance 
Code 
Instructions per Maintenance 
Code/Material Usage 
Subtask
Subtask/Subtask 
Subtask/Material List   
Modification Details
Modification Details/Instructions
Modification 
Details/Instructions/Material Usage 
Condition Monitoring Program
Condition Monitoring 
Program/Instructions 
Condition Monitoring 
Program/Instructions/Material Usage 
Instructions per Fault 
Function 
Instructions per Fault 
Function/Material Usage 
Serial Part Revision 
Serial Part Revision/Life Limit
Serial Part Revision/Life Limit/Material Usage
Post Maintenance Check Definition
Post Maintenance Check 
Definition/Instructions
Post Maintenance Check 
Definition/Instructions/Material Usage
Procedure
Use the following procedure to create a material line 
using the part revision for which the instruction is valid:
	- Open the 
	
	Instruction window and 
	query for your part revision.
- Click the  
	Material List tab and 
	create a new record (F5).
- In the Sub Part Number field, enter the 
	part number of the part that is to be included in the material list. Use the 
	List of Values to select a value.
- When the sub part number is selected, a value in 
	the Sub Part Revision field appears automatically. If this is not the 
	required sub part revision, use the List of Values to select another value.
- If the part is to be supplied by a manufacturer, enter the 
	manufacturer's number in the Manufacturer Number field. Use 
	the List of Values to select a value.
- If the part is to be supplied with a specific 
	manufacturer's part number, enter the value in the Manufacturer's Part 
	No field. Use the List of Values to select a value. 
- In the Quantity field, enter the quantity 
	of material (i.e., the selected part) that is to be used during the 
	execution of an operation.
- If the part will not be used every time the operation is executed, enter the probability 
	(as a percentage) of the part being needed in the Probability field.
- Save the record (F12).
Use the following procedure to create a material line 
using the manufacturer's part number:
	- Open the 
	
	Instruction window and 
	query for your part revision.
- Click the  
	Material List 
	tab and 
	create a new record (F5).
- In the Manufacturer's Part No field, enter 
	the manufacturer's part number that is to be included in the material list. 
	Use the List of Values to select a value.
- The corresponding sub part revision information 
	appears automatically in the Sub Part Number and Sub Part Revision 
	fields. If needed, use the List of Values to select another sub part 
	revision in the Sub Part Revision field.
- In the Quantity field, enter the quantity 
	of material (i.e., the selected part) that is to be used during the 
	execution of an operation.
- If the part will not be used every time the operation is executed, enter the probability 
	(as a percentage) of the part being needed in the Probability field.
- Save the record (F12).
Note: You can also define materials for an existing instruction in the following windows:
	
		- Instructions per Maintenance Code/Material 
	Usage
- Modification Details/Instructions/Material Usage
- Condition Monitoring 
Program/Instructions/Material Usage
- Instructions per Fault Function/Material 
	Usage
- Serial Part Revision/Life Limit/Material 
		Usage 
- Post Maintenance Check Definition/Instructions/Material Usage
Use the following procedure to define the material to 
be used on a subtask:
	- Open the Subtask window.
- Populate (F2) or query (F3) for the desired 
	subtask.
- Click the Material List tab and 
	create a new record (F5).
- Specify the sub part number and sub part revision 
	of the material. Use the List of Values in the relevant fields to select 
	valid values. You can also directly select the manufacturer's part number 
	for the material, thereby retrieving the sub part revision. 
- Enter the quantity of material required.
- Save the information (F12).