Explanation
This activity is used to connect a subtask to an 
instruction. You can choose to create and connect a subtask or to connect an 
existing subtask to the instruction. Subtasks are used to describe how the instruction should be 
performed. It is possible to connect several subtasks to an instruction. When a 
subtask is connected to an instruction, the following rules apply:
	- Number of persons for both the instruction and 
	connected subtask can be entered as a whole on the instruction. When this is 
	done, number of persons on the individual subtask line can be set to 0.
- Hour consumption for both the instruction and 
	connected subtask can be entered as a whole on the instruction. When this is 
	done, hour consumption on the individual subtask line can be set to 0.
- Material lists can be defined for both the 
	instruction and connected subtask.
- Tools and facilities can be defined for both the 
	instruction and connected subtask. However, the same Tool/Facility ID 
	cannot be entered on both the instruction and connected subtask.
- Zones and access panels cannot be defined for both 
	the instruction and subtask. Note that it is possible 
	to connect a subtask with zones to an instruction with zones if the 
	instruction is in the Preliminary status. However, when this 
	instruction is activated, the zones that are defined on the instruction will 
	be removed automatically.
- Signature requirements can be defined for both the 
	instruction and subtask. 
Prerequisites
	- Instructions must have been defined for the part 
	revision.
- Subtasks must have been defined for the same part 
	revision as the instruction.
System Effects
As a result of this activity, subtasks will be 
connected to an instruction. If the subtask being connected does not already 
exist, the subtask will be created. The subtasks will once again be transferred 
to the work order together with instructions.
Window
Instruction  
Related Window Descriptions
Instruction   
Instruction/Subtasks/Subtasks 
Procedure
	- Open the Instruction window.
- Populate (F2) or query (F3) for the desired 
	instruction.
- Click the Subtasks tab and then 
	click the Subtasks sub tab.
- Create a new record (F5).
- In the Subtask ID field, enter the ID of 
	the subtask. If you are connecting an existing subtask, use the List of 
	Values to select a valid value.
- If you are connecting an existing subtask, you 
	can complete the procedure by clicking OK.
- For new subtasks, enter a description of the 
	subtask in the Subtask Description field.
- In the Competence field, enter the required 
	competence. Use the List of Values to select a valid value.
- In the No of Persons field, enter the 
	number of persons required to perform the subtask.
- In the Hour Consumption field, enter the 
	hour consumption.
- In the Work Description field, enter a 
	description of the work to be done.
- Save the record (F12).