Perform Order Proposal
Explanation
The order proposal is used by a purchaser or planner to study the demand for 
inventory parts using planning method B - Order Point System, or planning method
C - Refill Level.
It is also possible to create and delete purchase requisitions, shop order requisitions
and create purchase orders and distribution 
orders. The supply type on the inventory part determines whether
a purchase order or a purchase requisition will be created by the order proposal. 
A distribution order will be created instead 
of a purchase order if the primary supplier for the part has Multi-site Planned 
Part selected. The
requisitions that can be deleted must have been created by the order proposal.
Some of the fields in the planning data that affect the order proposal are:
  - Planning Method - For a part to be processed by the order proposal, the 
	planning method must be B or C.
- Safety Stock - May be zero, but must be less or equal to the order point.
- Order Point - May be zero, but must be less or equal to the lot size.
- Lot Size - Only used for planning method B. Must be greater than 
	zero (0). If a quantity is
proposed by the order proposal it will be a multiple of the lot size.
    For example, the
	lot size equals 10 and the quantity needed is 12, the quantity proposed will be 20.
- Manufactured/Acquired Split - The 
	order proposal quantity could be split in accordance to the 
	Manufactured/Acquired Split percentage as defined on the inventory part. If 
	this split is used, one split quantity will be sent to manufacturing on a 
	shop order requisition and the 
	other split quantity will be sent to purchasing on a purchase requisition, 
	purchase order or distribution order.
  
The Advanced feature enables you to
specify additional selection criteria for records that will be included in the
order proposal.
 For example, delete old requisitions, create requisitions/orders, and process manufactured orders.
The Default feature allows you to use the default settings for this activity. 
Default settings are derived from the Database Tasks window set by 
the administrator. 
Note 1: Order proposal calculations only include standard inventory (i.e., project inventory balances are excluded).  
Note 2: If the available quantity is below the specified safety stock, the Order Proposal Planning functionality may still create duplicate supplies / supply proposals (i.e., when converting the generated requisition to purchase order with the due date falling within the purchase lead time).
Prerequisites
  - The inventory part must use planning method
    B - Order
    Point System, or C - Refill Level. This can be checked on the 
	Inventory
    Part/Planning Data tab.
- The part must exist in standard inventory.
- To have a distribution order created, 
	the supply type must be Order, and Multi-site Planned Part must be selected 
	for the primary supplier of the part.
  
System Effects
The system effects vary depending on which settings you have indicated.
  - If the Create Requisition/Order check box is selected, purchase 
	requisitions/orders, shop order requisitions, 
	or distribution orders will be created for the parts that are
processed. To decide which orders should be created, the  Lead Time Code in
the 
	Inventory
Part/Acquisition tab is considered. To decide whether purchase order 
	requisitions, purchase orders or 
	distribution orders should be created, the  Supply Type field on the 
	Inventory
Part/Planning Data  tab is considered.
- If the Delete Old Requisitions check box is
    selected, the purchase requisitions and shop order requisitions that were created
    previously, but have not been converted to orders by the order proposal
    feature as yet, and the distribution orders still in the Planned 
	status will be deleted.
- If the Process Purchased Parts check box is
    selected, purchase parts will be included in the calculation of the order
    proposal.
- If the Only Parts with Inventory Activity check
    box
    is selected, the order proposal will exclude parts that do not have any activity since
    the last order proposal review for the parts in question. Reserve, issue,
    move, receive, scrap, return parts, change planning data, or create pallets
    for parts are considered as activities performed on inventory parts.
- If the Calculate Planning Data Before Creating
    Order Proposals check box is selected, planning data will be calculated
    for selected parts prior to creating an order proposal.
- If the Process Manufactured Parts check box
    is selected, the manufactured parts will be included in the calculation of the
    order proposal.
  
Window
Create Order Proposal
Related Window Descriptions
Create Order Proposal
 Create Order
Proposal-Additional Parameters
Procedure
You can either create an order proposal directly
(procedure A) or schedule the task as a background job (procedure B).
A. To perform the create order proposal 
task directly:
  - Open the Create Order Proposal dialog box. 
- Enter a value for the Site field or click List
    to select one from the List of Values.
- If you want to use the part number, commodity
    group 2 or planner as a selection criteria, enter the appropriate values
    in the respective fields. Do this by entering values or click List 
    to select one from the List of Values. The wildcard character (%) can also be used to select a group of records. 
- Enter a value for the PO Coordinator field or
    click List to select one from the List of Values 
- If you want to specify additional selection criteria,
    click Advanced. You can choose from among the following
    additional selection criteria as appropriate: delete old requisitions
	and distribution orders that are not released as yet, create requisitions/orders,
    and process
    purchased parts. If you select the Calculate
    Planning Data Before Creating Order Proposals  check box, you can
    specify a value in the Periods field. 
- If the necessary selection criteria has been defined, click OK to complete
    the operation.
  
Note: Click Default if you want to use
the default settings. 
B. To schedule the create order proposal 
task as a background job: 
  - 
	
	Click Schedule to open the New Database Task Schedule 
	window. Set the scheduling parameters as desired and save. Scheduled tasks 
	can be seen in Scheduled Database Tasks window.