Move to New Transport Task
Explanation
This activity is used to move selected transport task lines to a new 
transport task.
Prerequisites
	- The transport task cannot be in the Executed status.
- The From and To sites must be the same for all transport task lines.
- The location group for the selected transport task lines must be the 
	same (for the From location).
- Transport task lines should not be included in a transport task with the
	Fixed check box selected.
System Effects
The selected transport task lines will be moved from the transport tasks to 
which they are currently connected, and placed in a new transport task. The ID 
of the new transport task is visible in the New Transport Task ID field 
in the New Transport Task dialog box.
Window
Transport Task
Transport Task Lines 
Related Window Descriptions
Transport Task
Transport Task Lines
Purchase Order Receipt
Purchase Order Receipt/Pallet
Move into QA
Move into Stock
Procedure
	- Open the Transport Task or the
	Transport Task Lines window.
- Select the transport task lines that should be moved.
- Right-click and then click Move to New Transport Task.
- Select the Set To Fixed check box to make sure that the new 
	transport task is not modified.
- Select the Print Transport Task check box to print the transport 
	task.
- Select the Open Transport Task check box to open the new 
	transport task once it is created.
- Click OK to create the new transport task.