Add Indirect Time Result
Explanation
Use this activity to manually register a time result for indirect labor spent 
on an indirect job.
Prerequisites
	- At least one indirect job must have been entered in Indirect Jobs 
	window.
- The Report Mode must have been set to Employee in the 
	Site window.
- At least one employee must have been entered in Manufacturing 
	Labor Class window.
System Effects
As a result of this activity an indirect labor transaction will be created.
Window
Time Card 
Day
Operation and 
Indirect Reports
Related Window Descriptions
Add Indirect Time Result
Operation and Indirect 
Reports
Procedure
To add indirect result:
	- Right-click and click Add Indirect Result.
- In the Site field, enter the site or use the list of values to 
	select the site on which the time should be registered. 
- In the Indirect Job field, use list of values to select the 
	indirect job on which the time should be registered.
- In the Date field, enter the date on which the time should be 
	registered.
- In the Employee field, enter the employee on which the time 
	should be registered.
- If applicable enter a team and a work center that the time should be 
	registered on.
To add operation result:
	- Right-click and click Add Operation Result.
- In the Operation ID field, enter the relevant operation identity or 
	select a value by clicking List.
- Enter values in Labor Setup and Labor Run fields.
- Click OK.