Create/Modify Resource Breaks
Explanation
This activity is used to create or modify a resource break. Resource breaks 
are taken into account only when orders are scheduled using Constraint Based Scheduling (CBS), not when using the Shop Order 
Infinite Scheduler.
Prerequisites
This activity requires the existence of a site to which you can connect the resource
break. Furthermore, you must have defined the resource to which the resource break
applies. 
System Effects
	- If you create a new resource break, it will be in Proposed state. 
	It cannot be loaded to the Advanced Planning Board (APB) while it is in this state.
- If you modify an existing resource break which is in Approved or
	Scheduled state, its state changes to Unscheduled.
Window
Resource Break
Advanced Planning Board
Related Window Descriptions
Resource Break
Advanced Planning Board
Procedure
  - In the 
	Resource Break window, select New to create a
    new resource break. Alternatively, query for an existing one.
- For a new resource break, enter the break number in the Break No field, or let the
    system define one automatically.
- Enter or modify a description for the resource break in the Break Description field.
- For a new resource break, specify the site at which the resource break will 
	be used in the
    Site field. Use the List of Values to select from available sites. The selected site
    may not be modified.
- For a new resource break, accept the default break type setting of Manual. The break
    type cannot be modified.
- In the Work Order field, accept the blank setting or the default value.This number cannot be specified for a manual break. It is system-supplied for a
    break that has been imported from IFS/Maintenance. 
- Enter or modify the break duration in the Break Duration field. This value is defined in
    hours.
- Enter or modify the range in which the resource break may be scheduled in the 
	Begin Date
    Range and End Date Range fields. The range must be large enough to accommodate the break
    duration.
- Perform one or more of these steps:
      - Enter or modify the work center resources for the resource break in the 
		Work
        Center Resources tab.
- Enter or modify the tool instances for the resource break in the 
		Tools
        tab.
- Enter or modify the labor class resources for the resource break in the 
		Laborers
        tab.
 
- Click Save to save the new or modified resource break.
- Whenever desired, change the status of the resource break by 
	right-clicking and then clicking one of the available 
  options as appropriate. These options include Approve, Discard, 
  Confirm, Schedule, Unschedule, and
    Complete.
 Note: For resource breaks in non-Constraint 
	Based Scheduling sites, the only options available are Approve, Discard,
	Reject and Complete.
Creating a resource break using the Advanced Planning Board:
	- Load the Advanced Planning Board and click the 
	Activities tab.
- Select the Resource Breaks node, right-click and 
	then click New Child. This will open the Create dialog 
	box.
- Enter a name for the resource break in the Name
	field.
- Click Resource Break. A new resource break 
	object will be created under the Resource Breaks node and the 
	Resource 
	Break window appears. The resource break 
	will be in Incomplete state.
- In the Show Status tab, enter 
	appropriate dates in the Need Date and EPST fields.
- Click the Show Contents tab and enter the break 
	duration in the Duration Time field.
- Enter a description in the Description field.
- Click the Show Assignment tab and 
	then click New Role.
- Drag and drop a resource from the Master 
	Data tab of the Advanced Planning Board to the Assigned 
	Resource field. You may add more than one role and a resource if 
	necessary.
- Drag and drop the resource break object into the 
	object table area.
- Select the object in the object table area, 
	right-click and then click Scheduling.
- In the Change Schedule dialog box 
	that appears, select the appropriate option in the When rescheduling this
	area and then click OK.