Specify Scheduling Settings for Scheduling Server
Explanation
Use this activity to define the different default time frames and other 
settings used by the Scheduling Server. You must also define how the scheduling 
server should assign load to the different resources. This mandatory task is to 
be performed by a system administrator or equivalent person. 
By specifying a transport calendar you can exclude non-working days when calculating the transport time. 
The transportation calendar takes effect only when shop order operations are 
scheduled and when the preceding operation or operations have a defined 
transportation time.
Prerequisites
There needs to be a valid connection between the Constraint Based Scheduling 
(CBS) site and the Scheduling Server.
System Effects
As a result of this activity the values you specify are used by the 
Scheduling Server to schedule operations.
Window
Scheduling Basic Data
Related Window Descriptions
Scheduling Basic Data 
Scheduling Basic Data/Shop Order Scheduling/General
Scheduling Basic Data/Shop Order Scheduling/Scheduling 
Server
Procedure
  - Open the 
	Scheduling Basic Data window.
- Populate the window or query for the site.
- In the Site field, select the site for which to define the default values.
- Click the 
	Shop Order Scheduling/Scheduling 
	Server tab. In the Host and Port fields in the 
	Communication Settings area, specify the host (the IP address is 
	preferred over the host name) and port (usually four digits) to be used for 
	the Shop Order Scheduling Server.
- In the Scheduling Horizon (Days) field, enter the number of days the Scheduling Server
    should use. This is the time period that will be 
	considered when constructing the schedule. Any operations that cannot be 
	included within this horizon will not be scheduled. The default value is 365. 
	The shorter the time frame the faster the scheduling process.
- In the Scheduling Startpoint (Hrs from Present Time) field,
    enter a default start time for the first operation in
    the schedule. This value is optional, with the default value of zero.
- In the Priority Adjustment Factor Weight field, enter a value to indicate
    the weight used for prioritization of shop orders. The default value is 1.
- In the Transport Calendar field, enter the 
	calendar or select a suitable calendar from the List of Values. This 
	calendar will be used to calculate the scheduled transport time. When 
	scheduling a shop order operation, the scheduled transport time will be used. 
      
 Note: If you want to view the
    transport 
	calendar, click Settings in the Scheduling Server and select Schedule Settings. The 
	Schedule Settings dialog box opens. To 
	view transport calendar details, double-click on the transport calendar 
	object. To get a graphical representation of the transport calendar, drag the 
	transport calendar object to the left of the Gantt chart.
 To view the scheduled 
	transport time of a single shop order operation, right-click 
	on the shop order operation object and click Show. The 
	Operations 
	dialog box opens. Click the Show 
	Contents 
	tab.
- In the Sequencing Horizon (Days) field, enter number of days. This is the
    value the system uses to specify default start and end dates in the
    Sequencing Assistant. The default value is zero.
- In the Setup Optimization section, select one of the three options to
    determine what factors the
    scheduling server will use to optimize setup.
- In the 
	Scheduling 
	Server tab, 
	select the Extend Shop Order check box in the Action When Lot Size 
	is Modified on Shop Order area, if you want shop orders to be expanded or 
	contracted according to changes to their scheduled time requirement. This 
	will be done without changing the current start time of the modified shop orders.
	Note: However in the following situations, the scheduled start time 
	is changed; 
	
		- If the expanded SO is scheduled in the past before expanding. 
- If the expanded SO affects a promised SO and cannot be scheduled 
		before it.
 
- In the Action When Buffered Operation Reporting is Enabled area, select 
	the Adjust Schedule Due To Shop Floor Reporting check box if you want 
	the schedule to be adjusted to reflect time reported on shop order 
	operations. You can use the options under this check box to indicate how you 
	want the schedule to be updated.
	
		- Prioritize Reported Operation - at the 
		next execution of buffered operations reporting, the reported operation 
		is given priority and scheduled as close as possible to now time.
- Keep Scheduled Operation Sequence - the 
		schedule will be updated according to shop floor reporting at the next 
		execution of buffered operations reporting, but without altering the 
		previous schedule sequence. Subsequent operations in the same order 
		structure will move closer to the reported operation in order to fill 
		any capacity gaps which occur immediately after the reported operation.
  - Save the record.