Completion Scrap with Catch Unit Enabled Components 
Explanation
This activity is used to handle completion of scrap, 
for catch unit enabled component 
parts in production schedules. A catch unit is enabled to allow a specific
inventory part to manage two parallel units of measure. Information regarding 
both quantities, inventory and catch, are saved on every inventory transaction
record. If the part to be scrapped consists of at least one catch unit 
enabled component part, the component quantity must be reserved so that it will be issued 
in both the inventory unit of measure (UoM) and the catch UoM, while scrapping the parent part.    
Prerequisites
	- A part can be reserved as a catch quantity only if it
is catch unit enabled. 
- If catch unit is enabled for the parent 
part, the quantity reported must have been entered in both the inventory UoM and catch UoM.         
System Effects
	- The reserved quantity in both catch UoM and inventory 
UoM will be issued during backflush.
- Inventory locations will be updated with 
issued quantities.  
Window
Production 
Receipt   
Production Schedule By Line 
Production Schedule By Line Part  
 
Related Window Descriptions
Production Receipt 
Production Schedule By Line  
Production Schedule By Line Part 
 
Procedure
From the 
Production Receipt window:
	- 
    Open the 
	Production Receipt window.
	
- 
    Populate or query for appropriate production line that 
	you want to report scrap for. 
- 
	Right-click and then click 
	Scrap Receipt. The
	Scrap Receipt dialog box will appear. 
- 
	In the Scrap Receipt dialog box, 
	select Immediate Backflush or  
	Defer Backflush in the  
	
	Backflush list. 
- 
	In the Sched 
	
	Option list, select 
	
	Unscheduled or Schedule. 
- 
	In the 
	Structure area, specify structure revision and the structure alternate. You can also 
    specify the routing revision and the routing alternate if you want. 
- 
	In the  Production Scrap 
	area, enter the 
	quantity scrapped in the Qty Scrapped field. Click the Scrap Reasons 
	field and then click List to select from the available scrap reasons. 
	If catch unit is enabled for the parent part, you have the choice of 
	entering scrapped catch quantities.
- 
	In the 
	Report Point area, select the 
	
	Complete Scrap check box to indicate that this is the complete scrap for 
	the manufacturing process. 
- 
	To edit the components, click 
	Components. The
	
	Production Receipt Material dialog box will 
	appear. 
	
- 
	In the 
	Production Receipt Material 
	dialog box, type a value in the Qty To Issue field. 
- 
	To change components, click 
	New. 
	The cursor appears in the Part To Issue field. Click  
	List to 
	select from the available parts. Next, type a value in the Qty To Issue 
	field.
	
- 
	Save. 
- 
	To reserve the components before backflushing, select 
	the components and then click 
	Assign. The 
	Production 
	Receipt Reservation dialog box will appear. 
- 
	In the 
	Production Receipt Reservation 
	dialog box, click Create. The 
	Inventory Part Location 
	dialog box will appear. 
- 
	In the 
	Inventory Part Location 
	dialog box, select a location. Click 
	
	OK. 
- 
	In the 
	Production Receipt Reservation 
	dialog box, enter a value in the Qty Assigned field.
	Save, then 
	click OK when the reservations are done. 
- 
	When you have finished editing and reserving the components, click 
	OK to run the
    backflush. 
 
From the 
Production Schedule by Line 
window:
	- 
	Open the 
	Production Schedule By Line 
	window. 
- 
	Populate or query for appropriate production line that 
	you want report scrap. 
- 
	Select the appropriate production 
	schedule for which you want to report scrap. Right-click and then select
	Scrap
    Receipt. The 
	Scrap Receipt 
	dialog box will appear. 
- 
	In the Scrap Receipt dialog box, 
	select  Immediate Backflush or 
	Defer Backflush in the  
	
	Backflush list.
- 
	Select 
	Unscheduled or 
	Schedule in 
	the Sched Option list.
- 
	In the  
	Structure 
	area, specify the structure revision and the structure alternate. You can also 
    specify the routing revision and the routing alternate if you want. 
- 
	In the 
	Production Scrap area, type the 
	quantity scrapped in the Qty Scrapped field. Click the Scrap Reasons 
	field and then click List to select from the available scrap reasons. 
	If the catch unit is enabled for the parent part, you can enter scrapped 
	catch quantities; however this is optional. 
- 
	In the 
	Report Point group box, select the 
	
	Complete Scrap check box to indicate that this is the complete scrap for 
	the manufacturing process. 
- 
	To edit the components, click 
	Components. The
	
	Production Receipt Material dialog box will 
	appear. 
	
- 
	In the 
	Production Receipt Material 
	dialog box, enter a value in the Qty To Issue field. 
- 
	To change components, click 
	New. 
	The cursor appears in the Part To Issue field. Click 
	List to 
	select from the available parts. Next, enter a value in the Qty To Issue
	field.
	
- 
	Save. 
- 
	To reserve components before backflushing, select the 
	components and then click Assign. The 
	Production Receipt 
	Reservation dialog box will will appear. 
- 
	In the 
	Production Receipt Reservation 
	dialog box, click Create. The 
	Inventory Part Location 
	dialog box will appear. 
- 
	In the 
	Inventory Part Location 
	dialog box, select a location. Click 
	OK. 
- 
	In the 
	Production Receipt Reservation 
	dialog box, enter a value in the Qty Assigned field.
	Save, then 
	click OK when the reservations are done.
- 
	When you have finished editing and reserving the components, click 
	OK to run the
    backflush. 
 
From the 
Production Schedule by Line Part 
window:
	- 
	Open the Schedule By Line Part window. 
	
- 
	Populate or query for appropriate Part No you 
	want to report scrap for. Then select the production 
	schedule for which to report scrap. Right-click 
	and then select 
	Scrap Receipt. The 
	Scrap Receipt 
	dialog box will appear.
- 
	In the Scrap Receipt dialog box, 
	select  Immediate Backflush or 
	Defer Backflush in the 
	 
	Backflush list.
- 
	In the Sched Option
	list, select  
	Unscheduled or Schedule. 
- 
	In the  
	Structure 
	area, specify the structure revision and the structure alternate. You can 
    also specify the routing revision and the routing alternate if you want. 
- 
	In the  Production Scrap 
	area, enter the 
	quantity scrapped in the Qty Scrapped field. Click the Scrap Reasons 
	field and then click 
	List 
	to select from the available 
	scrap reasons. If the catch unit is enabled for 
	the parent part, you can enter scrapped catch quantities; however this is 
	optional. 
- 
	In the  
	Report Point 
	area, select the 
	Complete Scrap check box to indicate that this is the complete scrap for 
	the manufacturing process. 
- 
	To edit the components, click 
	Components. The
	
	Production Receipt Material dialog box will 
	appear. 
	
- 
	In the 
	Production Receipt Material 
 dialog box, enter the quantity to issue in the Qty To Issue 
	field.
	
- 
	To change components, click 
	New. 
	The cursor appears in the Part To Issue field. Click 
	List to 
	select from the available parts. Next, enter a value in the Qty To Issue 
	filed.
	
- 
	Save. 
- 
	To reserve the components before backflushing, select 
	the components and then click 
	Assign. The 
	Production 
	Receipt Reservation dialog box will appear. 
- 
	In the 
	Production Receipt Reservation 
	dialog box, click Create. The 
	Inventory Part Location 
	dialog box will appear. 
- 
	In the 
	Inventory Part Location 
	dialog box, select a location. Click 
	OK.
- 
	In the 
	Production Receipt Reservation 
	dialog box, enter a value in the Qty Assigned field.
	Save and then 
	click OK when the reservations are done. 
- 
	When you have finished editing and reserving the components, click 
	OK to run the
    backflush.