Enter Inspection Results
Explanation
This activity is used to enter the inspection results 
 once 
an inspection is completed. The inspection information cannot be updated after the Inspection Line Completed check
box is selected. 
Prerequisites
The material review board (MRB) case must have one or 
more inspection lines entered.  
System Effects
	- An inspection line will be updated to the Completed 
	status. 
- If you attempt to select the Inspection Line 
	Completed check box without entering the inspection results, a 
	message will be displayed prompting you to enter at least one inspection 
	detail to complete the inspection line. 
- Information will be automatically displayed in the
      Completion Date and the Completed By fields.  
Window
MRB Case
Related Window Descriptions
MRB Case
 
MRB Case/Inspection
Procedure
	- Open the MRB Case 
	window.
- Query or populate for the required MRB case ID. 
- Click the 
	Inspection tab.
- Enter the inspection results in the Inspection 
	Result field. 
- Save the record.
- Then select the Inspection Line Completed 
	check box. 
- Save the record.