Receive Byproducts from Production Receipt, Production Scrap
Explanation
Use this activity to receive byproducts at the end of the production receipt, report point receipt or scrap receipt. You can add, edit or remove byproducts from the production receipt materials accordingly. These are issued when the
backflush occurs.
Prerequisites
	- This activity requires that scheduled quantities for the part exist. 
- A part must be associated with a production line. 
- Issuing part should have the byproducts defined at the parent level.
System Effects 
	- As a result of this activity the system backflushes the components and the operations used in the manufacturing process.
- If making a scheduled receipt, the system automatically updates the production schedule.
- If making an unscheduled receipt, the system does not automatically update the production schedule.
- Received quantity will consist byproducts and parts to be issued both.
Window
Production
Receipt
Production
Schedule By Line
 
Production Schedule
By Line Part
Related Window Descriptions
Production Receipt  
Production Schedule by Line
 
Production Schedule by Line Part
 
Procedure
From the 
Production Schedule by Line window:
  - Open the  
	Production Schedule By Line window. 
	
-  In the Production Line list, select the part for which to report production.
- Select the production schedule line for which to report production. 
  Right-click and then click Production Receipt. The 
	Production Receipt 
	dialog box will appear.
- In the 
	Production Receipt dialog box, specify how many parts you
    want to report and receive into inventory in the  Qty Reported field. The scheduled
    quantity is the default value. If the part is catch
    unit enabled, enter the catch quantity 
	received in the Received Catch Qty field.
 
- In the  Sched Option   list, select 
	Scheduled or Unscheduled.
- In the Backflush list, select Immediate 
	Backflush or Defer
    Backflush.
- In the Structure area, specify the part revision
    and structure alternate. If desired, you can specify the routing revision and the routing
    alternate.
- In the Location area, select the Complete check box to create a
    complete production receipt.
- In the Location area, click in the  Location No field, then click
    List
    to choose from different inventory locations. 
- To receive byproducts, click Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material dialog box, type a value in the
    
    Qty To Issue field as a negative value to receive the needed byproduct. 
- To receive a byproduct seperately, create a new record. The cursor appears in the  Part To Issue
    field. Click List to select from available parts. Next, type a value in negative in the
     Qty to
    Issue field.
    
 Note: To define the byproducts quantity for a particular part, you have to have it defined at the product structure level for the given part.
- When you are finished with selecting the needed quantity of byproducts, click OK to run
    the backflush.
- If you want to receive byproducts at the production scrap, select the Part No list, right-click and select Scrap Receipt. Scrap Receipt dialog box will open.
- In the  Sched Option   list, select 
	Scheduled or Unscheduled.
- Define the scrap quantity in the Qty To Scrap field. Also define the Scrap Reason and click Components. The 
	Production Receipt
    Material dialog box will appear.
- Continue from step 11 to 13 to get the byproducts.
From the  Production Schedule by Line Part window: 
  - Open the  
	Production Schedule By Line Part window. 
	
-  In the Part No list, select the part for which to report production.
- Select the production schedule line for which to report production. 
  Right-click and then click Production Receipt. The 
	Production Receipt 
	dialog box will appear.
- In the 
	Production Receipt dialog box, specify how many parts you
    want to report and receive into inventory in the  Qty Reported field. The scheduled
    quantity is the default value. If the part is catch
    unit enabled, enter the catch quantity 
	received in the  Received Catch Qty field.
 
- In the  Sched Option   list, select 
	Scheduled or Unscheduled.
- In the Backflush list, select Immediate 
	Backflush or Defer
    Backflush.
- In the Structure area, specify the part revision
    and structure alternate. If desired, you can specify the routing revision and the routing
    alternate.
- In the Location area, select the Complete check box to create a
    complete production receipt.
- In the Location area, click in the  Location No field, then click
    List
    to choose from different inventory locations. 
- To receive byproducts, click Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material dialog box, type a value in the
    
    Qty To Issue field as a negative value to receive the needed byproduct. 
- To receive a byproduct seperately, create a new record. The cursor appears in the  Part To Issue
    field. Click List to select from available parts. Next, type a value in negative in the
     Qty to
    Issue field.
    
 Note: To define the byproducts quantity for a particular part, you have to have it defined at the product structure level for the given part.
- When you are finished with selecting the needed quantity of byproducts, click OK to run
    the backflush.
- If you want to receive byproducts at the production scrap, select the Part No list, right-click and select Scrap Receipt. Scrap Receipt dialog box will open.
- In the  Sched Option   list, select 
	Scheduled or Unscheduled.
- Define the scrap quantity in the Qty To Scrap field. Also define the Scrap Reason and click Components. The 
	Production Receipt
    Material dialog box will appear.
- Continue from step 11 to 13 to get the byproducts.
From the 
Production Receipt window: 
  - Open the Production Receipt window. 
- In the item list, select the production line part for which you want to define or get the byproducts.
- Give the production issue quantity of the item in the Qty Received field
 Note: Defined quantity should not exceed the scheduled quantity
- Select Edit Components check box and click Save.
- In the Production Receipt Material dialog box, you can add and remove items to receive by using New and Remove buttons accordingly.
- In order to receive byproducts, you need to add an item line by using New button.
- In the item line define the part in the Part To Issue  field. You can use List of Values to get the needed part
- You have to define the byproduct quantity to be received at the report point or at the production 
	receipt, in the Qty To Issue field by giving a needed quantity as a negative value.
  
 Note: To define the byproducts quantity for a particular part, you have to have it defined at the product structure level for the given part.
- Click Ok after doing all the necessary changes.
- Byproduct quantity to be added will be added and shown in the Quantity On Hand in the Production Receipt window.