Report Point Scrap
 
Explanation
 
This activity is used to declare scheduled report point scrap that occurred on the produced
parts during the manufacturing process.
Note: Labor and operation setup time for each receipt is calculated as;
 
[(setup time/standard lot size)*receipt quantity]
If standard lot size is not defined, then the total setup time will be reported for every receipt. 
 
Prerequisites
 
	- This activity requires that a production schedule exists. 
- Report points must be defined
for the production line. 
System Effects
 
	- As a result of this activity, the system reports scrap for the parent part.
- Next, it
runs the backflush process to consume the components used up to a defined report point.
	
- The user can specify whether the backflush process is run directly or in the background by
selecting Immediate Backflush 
	or Defer Backflush in the 
	Backflush list. 
- The report point balance is not updated for the specific report point when
scrapping.
- If a routing is defined, all operation steps falling between this report point
and the previous one are scrapped at standard cost. 
- Operation-linked components used by
the reported operations are scrapped. 
- Material not linked to operations is assumed to be
required at the start of production. Thus, it is backflushed at the first report point. 
	
- If
inbound locations are defined, they are used by backflush in its search hierarchy. 
	
- If an
alternate component substitution sequence is defined, it is used by backflush when issuing
material.
- Inventory transactions are created for the scrap receipt and all issued
components.
- Operation history transactions are created for any backflushed machine or
labor operations. 
 
 
Window
 
Report
Point Receipt 
Production
Receipt 
Production
Schedule by Line 
Production Schedule
by Line Part
 
Related Window Descriptions
 
Report Point Receipt
Production Receipt   
Production Schedule by Line 
Production Schedule by Line Part 
Scrap Receipt
 
Procedure
 
From the Report Point Receipt/Production Receipt window:
 
  - Open the Production Receipt window.
- In the Production Line list, select the production line and part for which
    to report scrap.
- Right-click and then click Scrap Receipt. The Scrap Receipt
    dialog box will appear.
- In the Scrap Receipt window, select 
	Immediate Backflush
    or Defer Backflush in the 
	Backflush list.
- In the  Structure area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the Production Scrap 
  area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click  
	List to select from
    available scrap reasons.
- In the  Report Point area, select the 
	Partial Scrap check box to
    declare a partial scrap at a report point. 
- In the Report Point area, specify the report point in the 
  Report
    Point ID field. Click 
	List to select from available report
    points.
- Click OK.
From the Production Schedule by Line window:
 
  - Open the Schedule by Line window.
	
- In the  Production Line list, select the production line for which to report
    scrap.
- Select the production schedule for which you want to report scrap. 
  Right-click and then click 
  Scrap Receipt. The Scrap Receipt 
	dialog box will appear.
- In the Scrap Receipt window, select 
	Immediate Backflush
    or  Defer Backflush in the 
	Backflush list.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the  Production Scrap area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click 
	List to select from
    available scrap reasons.
- In the Report Point area, select the 
	Partial Scrap check box to
    declare a partial scrap at a report point. 
- In the Report Point area, specify the report point in the 
	Report
    Point ID field. Click 
	List to select from available report
    points.
- Click OK.
From the Production Schedule by Line Part window:
 
  - Open the Schedule by Line part window.
- In the Part No list, select the part for which you want to report scrap.
- Select the production schedule for which you want to report scrap. 
	Right-click and then
    select Scrap Receipt. The Scrap Receipt 
	dialog box will appear.
- In the Scrap Receipt window, select 
	Immediate Backflush
    or  Defer Backflush in the  
	Backflush list.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the Production Scrap 
  area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click 
	List to select from
    available scrap reasons.
- In the Report Point 
  area, select the 
	Partial Scrap check box to
    declare a partial scrap at a report point. 
- In the Report Point area, specify the report point in the 
	Report
    Point ID field. Click 
	List to select from available report
    points.
- Click OK.