Report Point Scrap with Catch Unit Enabled Components  
Explanation
This activity is used to handle report point scrap for 
Catch Unit (CU) enabled component parts in the production schedules. A catch unit is enabled to allow a specific
inventory part to manage two parallel units of measure. Information regarding 
both quantities, inventory and catch, are saved on every inventory transaction
record. 
Prerequisites
	- A part can be reserved as a catch quantity only if it
is catch unit enabled. 
- If catch unit is enabled for the parent part, the 
quantity reported must have been entered in both the inventory unit of measure (UoM) and
the catch UoM.
- If the parent part consists of one or more catch 
	unit enabled component parts, the catch unit enabled component parts must 
	have been reserved before running the backflush.            
System Effects
	- The reserved quantity will be issued in both the catch UoM and
the inventory 
UoM during backflush.
- Inventory locations will be updated with 
issued quantities.
Window
Production 
Receipt
Report Point Receipt 
Production 
Schedule By Line  
Production Schedule By Line Part 
Related Window Descriptions
Production 
Receipt
Report Point Receipt
Production Schedule By Line  
Production 
Schedule By Line Part   
  
Procedure
From the 
Production Receipt/Report 
Point Receipt window:
  - Open the 
	Report Point Receipt window.
	
- In the Production Line list, 
    select the production line and part for which to report scrap. Right-click 
    and then click Scrap Receipt. The 
	Scrap
    Receipt dialog box will appear.
- In the 
	Scrap Receipt 
	dialog box, select  
	Immediate Backflush
    or  Defer Backflush in the 
	Backflush list.
- In the  
	Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the  
	Production Scrap 
  area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click 
	List to select from
    available scrap reasons. If the part is catch unit 
	enabled, enter the quantity to be scrapped in the Catch Qty Scrapped field. 
    
- In the Report Point 
  area, select the 
	 Partial Scrap check box to
    declare a partial scrap at a report point. 
- In the Report Point 
  area, specify the report point in the 
	Report
    Point ID field. Click  
	List to select from available report points.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material 
	dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the
    Part To Issue field. Click 
	List to select from available parts. Next, type a
    value in the Qty To Issue field. 
- 
  Save.
- To reserve the components before backflushing, select the components, then click
   Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation 
	dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear. 
- In the 
	Inventory Part Location 
	dialog box, select a location.
    Click OK.
- In the 
	Production Receipt Reservation 
	dialog box, type a value in
    the Qty Assigned field. Also enter the catch quantity that you want 
	to reserve in the Catch Qty Assigned field.  
	
- 
    Save.
- When you are finished editing and reserving components, click 
	OK to run the
    backflush.
From the 
Production Schedule By Line 
window:
  - Open the 
	Production Schedule by Line 
	window. 
- In the  
	Production Line list, select the production line for which to report
    scrap.
- Select the 
  production schedule for which to report scrap. Right-click and then click Scrap
    Receipt. The 
	Scrap Receipt dialog box will appear.
- In the 
	Scrap Receipt 
	dialog box, select  
	Immediate Backflush
    or Defer Backflush in the 
	Backflush list.
- In the 
	Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the  
	Production Scrap 
  area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click 
	List 
	to select from available scrap reasons. If the part is
    catch unit enabled, enter the quantity to be scrapped in the Catch Qty 
	Scrapped field.
    
- In the Report Point 
  area, select the 
	 Partial Scrap check box to
    declare a partial scrap at a report point. 
- In the 
	Report Point 
  area, specify the report point in the 
	Report
    Point ID field. Click 
	List to select from available report points.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material 
	dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the
    Part To Issue field. Click  
	List 
	to select from available parts. Next, type a
    value in the Qty To Issue field. 
- 
  Save.
- To reserve the components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appear. 
	Also enter the catch quantity that you want to reserve in the Catch Qty Assigned field.  
	
- In the 
	Production Receipt Reservation 
	dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear. 
- In the 
	Inventory Part Location 
	dialog box, select a location.
    Click OK.
- In the 
	Production Receipt Reservation 
	dialog box, type a value in
    the Qty Assigned field. Save.
- When you are finished editing and reserving components, click 
	OK to run the
    backflush.
From the 
Production Schedule by Line Part 
window:
  - Open the 
	Production Schedule by Line Part 
	window. 
- In the Part No list, select the part for which to report scrap.
- Select the 
  production schedule for which to report scrap. Right-click and then click Scrap
    Receipt. The 
	Scrap Receipt dialog box will appear.
- In the 
	Scrap Receipt 
	dialog box, select 
	Immediate Backflush
    or Defer Backflush in the 
	Backflush list.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the Production Scrap 
  area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click 
	List to select from
    available scrap reasons. If the part is catch unit 
	enabled, enter the quantity to be scrapped in the Catch Qty Scrapped field.
    
- In the  
	Report Point 
  area, select the 
	 Partial Scrap check box to
    declare a partial scrap at a report point. 
- In the Report Point 
  area, specify the report point in the 
	Report
    Point ID field. Click  
	List to select from available report points.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material 
	dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the
    Part To Issue field. Click 
	List to select from available parts. Next, type a
    value in the Qty To Issue field. 
- 
  Save.
- To reserve the components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation 
	dialog box, click 
	Create. The 
	Inventory Part Location 
	dialog box will appear. 
- In the 
	Inventory Part Location 
	dialog box, select a location.
    Click OK.
- In the 
	Production Receipt Reservation 
	dialog box, type a value in
    the Qty Assigned field. Also enter the catch quantity that you want 
	to reserve in the Catch Qty Assigned field.    
- 
    Save.
- When you are finished with editing and reserving components, click 
	OK to run
    the backflush.