Reschedule Shop Order Material Line Using Drag-and-Drop
Explanation
This activity is used to reschedule a shop order 
material line and optionally the shop order operation requiring the material using 
drag-and-drop functionality from a visualization chart.
Prerequisites
N/A
System Effects
	- The shop order material line will receive a new 
	Required Date according to the 
	value provided in the dialog box.
- If the check box Reschedule Shop Order 
	Operation(s) is not selected and the new Required Date is later 
	than the Finish Date of the operation which to the material line is 
	connected, the operation connection will be removed. 
- If the check box Reschedule Shop Order 
	Operation(s) is not selected, the new Required Date may not be 
	later than the Finish Date of the shop order.
If the Reschedule Shop Order Operation(s) 
check box is selected:
	- Schedule Direction for the operation which 
	to the material line is connected will be set to Forward Scheduling and the operation will be rescheduled to start the first 
	available work date/time from the given value. If the material line is not 
	connected to any operation the first operation will be considered.
- Operations parallel to, and succeeding the rescheduled operation will 
	also be set to Forward Scheduling and rescheduled.
If the new Required Date is later than the 
original date, the Compress Operations check box can be selected. If 
selected operations preceding the rescheduled operation will be set to 
	Backwards Scheduling 
	and rescheduled with a Finish Date 
	adjacent to the rescheduled 
	operations new Start Date.
	- If the site is CBS server enabled, it is only possible to change the 
	Required Date of the material. Rescheduling of operations ( with or 
	without compress operations ) is not possible as scheduling individual 
	operations will be handled by CBS server logic and date required is not an 
	input for operation scheduling. For CBS , Material cumulative lead time, 
	scheduling capacity setting in the inventory part , supplies and demand 
	situations for the part will determine the material constraint when 
	scheduling. 
Window
N/A
Related Window Descriptions
Reschedule Shop Order Material Line
Related Visualization Chart Descriptions
	Inventory Part Availability Planning
Procedure
	- Open a visualizer enabled window and query for the site needed.
- If the Data View is displayed, click 
	Visualization View on the title bar. 
	
- Right-click and select
	Select Visualization. 
	The 
	Select Visualization dialog box will be 
	opened.
- Double-click Inventory Part Availability 
	Planning.
- Select the segment representing 
	the shop order material line demand you want to reschedule to a new 
	date.
- Click and hold the left mouse 
	button while moving the cursor. Release at the date to which you want 
	the material line to be rescheduled. The 
	Reschedule Shop 
	Order Material Line dialog 
	box will be opened.
- The date where released is defaulted as the new 
	Required Date, but can be optionally edited.
- Optionally select the Reschedule Shop Order 
	Operation(s) check box to reschedule also the operation which to the 
	material line is connected.
- Optionally select the Compress Operations 
	check box if you want to avoid slack between the operations.
- Click OK.