Scheduled Receipt
 
Explanation
 
This activity is used to report production. This is the standard activity for the reporting
process. After a finished part or subassembly is produced, the part is ready to go into
inventory. 
Note: Labor and operation setup time for each receipt is calculated as;
 
[(setup time/standard lot size)*receipt quantity]
If standard lot size is not defined, then the total setup time will be reported for every receipt. 
 
Prerequisites
 
This activity requires the existence of a production schedule. Scheduled quantities for
the part must exist. A part must be associated with a production line.   
 
System Effects
 
As a result of this activity, the system backflushes the components and operations used
in the manufacturing process. When selecting a scheduled receipt, the system automatically
updates the production schedule. If inbound locations are defined, they are used by the
backflush process in its search hierarchy. If outbound locations are defined, they are
used as default receiving locations for production associated with the production line. If
an alternate component substitution sequence is defined, it is used by the backflush
process when issuing material. Inventory transactions are created
for the receipt, as well as all issued components.  
Operation history transactions will be created for backflushed machine or labor operations. Quantities of the backflushed parts, 
received and issued in catch unit, will be saved on the record if 
it is entered.  
 
Window
 
Production
Receipt 
Production
Schedule by Line 
Production Schedule
by Line Part
 
Related Window Descriptions
 
Production Receipt 
Production Schedule by Line 
Production Schedule by Line Part
 
Procedure
 
From the Production Receipt window:
 
  - Open the Production Receipt window.
	
- In the Production Line list, select the production line and part for which
    to report production.
- To make a scheduled receipt, select  Scheduled 
	in the Sched Option 
  list.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the Backflush list, select 
	Immediate Backflush or 
	Defer
    Backflush.
- In the Location area, click in the 
	Location No field, then click List
    to choose from different inventory locations. Next, type the quantity to receive in the
    Quantity Received field. Material can be received into more than one inventory location. 
	If the part is catch unit enabled, the catch quantity should also be 
	entered in the Catch Quantity Received field.
 
- To change inventory locations, click 
	New. Click in the Location No 
	field, then
    click List to choose from available locations. In the 
	Quantity Received field, type the quantity of parts to receive. 
- Save.
From the Production Schedule by Line window:
 
  - Open the Production Schedule by Line 
	window. 
- In the Production Line list, select the production line and part for which
    you want to report production.
- In the table in the lower part of Production Schedule by Line 
	window, select the production schedule line for which to 
  report production. Right-click and then click Production Receipt. The Production Receipt
    dialog box will appear.
- In the Production Receipt dialog box, type the quantity of parts
    to report and receive into inventory in the Qty Reported field. The scheduled quantity is
    the default value. If the part is catch unit enabled, 
	the catch quantity should also be entered in the Catch Qty Reported 
	field.
    
- In the Sched Option list, select 
	 Scheduled to make a scheduled
    receipt.
- In the Backflush list, select 
	 Immediate Backflush or 
	Defer
    Backflush.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the Location area, select the 
	Complete check
    box to create a complete production receipt.
- In the Location area, click in the Location No field, then click 
	List
    to choose from different inventory locations. This determines the inventory location where
    parts are received. 
- Click OK.
From the Production Schedule by Line Part window:
 
  - Open the Production Schedule by Line Part 
	window. 
- In the Part No list, select the part for which you want to report
    production.
- In the table in the lower part of  Production Schedule by Line
	 Part 
	 window,
    select the production schedule line for which to report production. 
	Right-click and then select 
	Production Receipt. The Production Receipt
    dialog box will appear.
- In Production Receipt 
	window, type the quantity of parts to report
    and receive into inventory in the Qty Reported field. The scheduled quantity is the
    default value. If the part is catch unit enabled, the 
	catch quantity should also be entered in the Catch Qty Reported 
	field.
 	
- In the  Sched Option list, select 
	Scheduled to make a scheduled
    receipt.
- In the Backflush list, select 
	Immediate Backflush or 
	Defer
    Backflush.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- Select the Complete 
	check box to create a complete production
    receipt.
- In the Location area, click in the Location No field, then click 
	List
    to choose from different inventory locations. This determines the inventory location where
    parts are received. 
- Click OK.