Scheduled Scrap
 
Explanation
 
This activity is used to declare scheduled scrap that occurred on the produced parts during
the manufacturing process. For catch unit enabled parts, if 
the parent part comprises of one or more catch unit (CU) enabled components, the
CU enabled components have to be reserved before backflush is performed.
Note: Labor and operation setup time for each receipt is calculated as;
 
[(setup time/standard lot size)*receipt quantity]
If standard lot size is not defined, then the total setup time will be reported for every receipt. 
 
Prerequisites
 
This activity requires that a production schedule exists.
 
System Effects
 
	- As a result of this activity, the system reports scrap for the parent part and runs the
backflush process to consume the components. The user specifies whether the backflush
process is run directly or in the background. 
- If inbound locations are defined, they
are used by backflush in its search hierarchy. 
- If an alternate component substitution
sequence is defined, it is used by backflush when issuing material. 
- When reporting a
scheduled scrap, the system automatically updates the production schedule.
- Inventory transactions are created for the scrap receipt and all issued
components. 
- Operation history transactions are created for any backflushed machine or
labor operations. 
- If CU enabled 
component parts exist in the schedule, a message will appear informing you of 
	the CU enabled component parts in the schedule.  
Window
 
Production
Receipt 
Production
Schedule by Line 
Production Schedule
by Line Part
 
Related Window Descriptions
 
Production Receipt 
Production Schedule by Line 
Production Schedule by Line Part 
Scrap Receipt
 
Procedure
 
From the  
 
Production Receipt 
window: 
 
  - Open the Production Schedule window.
	
- In the Production Line list, select the production line and part for which
    to report scrap.
- Right-click and then click 
	Scrap Receipt. The Scrap Receipt 
	dialog box will
    appear.
- In the Scrap Receipt dialog box, select 
	Immediate Backflush
    or Deferred Backflush in the 
	Backflush list.
- In the  Sched Option list, select 
	Scheduled.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the  Production Scrap area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click  
	List to select from
    available scrap reasons. If the part is catch unit enabled, 
	the catch quantity should also be entered. 
 
- In the Report Point area, select the 
	Complete Scrap check box to
    specify that this is the complete scrap for the manufacturing process.
- Click OK.
From the  
 
Production Schedule by Line 
window: 
 
  - Open the Production Schedule by Line 
	window.  
- In the  Production Line list, select the production line for which to report
    scrap.
- In the table in the lower part of Production Schedule by Line 
	window,
    select the production schedule for which you want to report scrap. 
	Right-click and then click 
	Scrap Receipt. The Scrap Receipt 
	dialog box will appear.
- In the Scrap Receipt dialog box, select 
	Immediate Backflush
    or Deferred Backflush in the 
	 Backflush list.
- In the  Sched Option list, select 
	Scheduled.
- In the  Structure area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the Production Scrap area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click  
	List to select from
    available scrap reasons. If the part is catch unit enabled, 
	the catch quantity should also be entered in the Catch Qty Scrapped 
	field.  
 
- In the Report Point 
  area, select the 
	Complete Scrap check box to
    specify that this is the complete scrap for the manufacturing process.
- Click OK.
From the  
 
Production Schedule by Line Part 
window: 
 
  - Open the Production Schedule by Line Part 
	window. 
- In the Part No list, select the part for which to report scrap.
- In the table in the lower part of Production Schedule by Line
	 Part 
	window,
    select the production schedule for which you want to report scrap. 
	Right-click and then select 
	Scrap Receipt. The Scrap Receipt 
	dialog box will appear.
- In the Scrap Receipt dialog box, select  
	Immediate Backflush
    or  Deferred Backflush in the 
	Backflush list.
- In the Sched Option list, select 
	Scheduled.
- In the  Structure area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the  Production Scrap area, type the quantity scrapped in the Qty
    Scrapped field. Click in the Scrap Reasons field, then click 
	List to select from
    available scrap reasons. If the part is catch unit enabled, 
	the catch quantity should also be entered in the Catch Qty Scrapped 
	field. 
 
- In the Report Point area, select the 
	Complete Scrap check box to
    specify that this is the complete scrap for the manufacturing process.
- Click OK.