Start Production
Explanation
This activity is used to register that a production has started on one or 
several operations. It is possible to register both labor and machine time.
The start time and the stop time of a setup will be recorded. The clocking 
sequence is a unique number that will be set for each line that is started. Same 
clocking sequence will be set for all operations that are started at the same 
time.
From time clock, you can start production for only one 
operation at a time.
Prerequisites
	- The status of the operation should not be Planned or Closed.
- The status of the shop order should not be Parked. 
- To start labor time, a labor class must be connected to the operation in 
	the Shop Order window.
- To start machine time, a valid resource must exist on the work center.
- If Reporting Mode has been set to Employee Reporting on 
	the used site, at least one Employee must be entered in order to 
	report labor time.
- If an employee competency requirement 
	exists for the operation, and the competency check for the site is 
	mandatory, then the reporting employee(s) must have those competencies. 
- To report from time clock, employee should be a 
	time clock user. When reporting as a team, all the employees in the team 
	should be time clock users.
System Effects
	- If the Machine Time check box has been selected, a Machine 
	Clocking will be created and the start time recorded on it.
- If the Labor Time check box has been selected, one labor clocking 
	will be created for each Employee that has been entered in the Employee 
	list and the start time will be recorded on it. If no Employee is entered, 
	one clocking record will be created.
- The start time will be recorded on the clocking. 
	The clockings can be viewed in the 
	Clockings tab. 
- The operation will be marked with a cogwheel symbol 
	to the left in the operation list. If several operations was started 
	together the cogwheel will be complemented with a chain link.
- If the operation was marked with a exclamation mark for 
	interruption, this symbol will be now removed.
- The status of the operation is set to In Process.
- If an ongoing setup activity exists, it will be stopped.
- If the employee or team was running an indirect job this will be 
	stopped.
- If a machine clocking is already running on the resource where this one 
	is started and the Allow Concurrent Operations check box in the 
	Work Center window is cleared this machine clocking will be 
	stopped.
- The selected resource will be set as the preferred resource for the 
	operation.
Window
Shop Floor Workbench
Time Clock
Related Window Descriptions
Shop Floor Workbench
Start Production
Time Clock
Procedure
	- Open the Shop Floor Workbench  window. If Reporting Mode 
	has been set to Employee Reporting on the used site an employee or team must 
	have been entered in the Enter As dialog box.
- Click Refresh. The operations will be displayed according to the 
	filter that is being used.
- Select the operation lines for which you wish to start production, and click
	Start Production. 
- The Start Production dialog box will be opened. Based on 
	the data entered in the Shop Order window, Machine Time 
	and Labor Time options will be selected. You can change the values if 
	you want to. 
- Choose the resource which on the operation will run in the Resource 
	list.
- If run in Employee Reporting mode, enter the employees that will 
	work with the operation in the Employee table. If run in Anonymous 
	mode; enter the crew size manually. If a team is entered in Shop Floor 
	Workbench, 
	the employees currently in the team will be displayed and may not be 
	changed. 
- Click OK. The start time can be viewed in the Clockings 
	tab.
 
To perform this activity from Time Clock
	- Click the Start Production button in Time 
	Clock.
- Enter the Employee ID or the Team.
- Enter the Operation ID you want to start 
	production for.
- If machine run time exists for the operation, 
	Machine Time will be automatically set to Yes. Set it to No 
	if you do not want to start machine time.
- Choose the resource on which the operation will run in the
	Resource ID.
- If the existing clockings for the employee should 
	be stopped, select Yes in Stop Emp Clockings. The default 
	value is set based on the value of Allow Concurrent Operations for 
	the employee in Manufacturing Labor Class/Employee tab.
- Click OK.