Start Setup
Explanation
This activity is used to register that a set up has started on one or several 
operations. It is possible to register both labor and machine time.
The start time and the stop time of a setup will be recorded. The clocking 
sequence is a unique number that will be set for each clocking record that is 
created, however the same clocking sequence will be set for all operations that 
are started at the same time.
From time clock, you can start setup for only one 
operation at a time.
Prerequisites
	- The status of the operation is not Planned or Closed.
- The status of the shop order should not be Parked. 
- Neither a production nor set up activity is already running for the 
	particular operation. 
- To start labor time, a labor class must be connected to the operation in 
	the Shop Order window.
- To start machine time, a valid resource must exist on the work center.
- If Reporting Mode has been set to Employee Reporting on 
	the used site at least one Employee must be entered in order to 
	report labor time.
- If an employee setup competency requirement 
	exists for the operation, and the competency check for the site is 
	mandatory, then the reporting employee(s) must have those competencies. 
- To report from time clock, employee should be a 
	time clock user. When reporting as a team, all the employees in the team 
	should be time clock users.
System Effects
	- If the Machine Time checkbox has been selected, a Machine 
	Clocking will be created and the start time recorded on it.
- If the Labor Time checkbox has been selected, one Labor 
	Clocking will be created for each Employee that has been entered in the
	Employee List and the start time will be recorded on it. If no 
	Employee is entered, one clocking will be created.
- The start time will be recorded on the clocking. 
	The clockings can be viewed in the  
	Clockings tab. 
- The operation will be marked with a monkey wrench symbol to 
	the left in the operation list. If several operations was started together 
	the monkey wrench will be complemented with a chain link.
- If the operation had an exclamation mark for 
	interruption, this symbol is now removed.
- The status of the operation is set to Setup Started.
- If the employee or team was running an indirect job, this will be 
	stopped.
- If a machine clocking is already running on the resource where this one 
	is started and the Allow Concurrent Operations check box in the 
	Work Center window is cleared this machine clocking will be 
	stopped.
- The selected resource will be set as the preferred resource for the 
	operation.
Window
Shop Floor Workbench
Time Clock
Related Window Descriptions
Shop Floor Workbench
Start Setup
Time Clock
Procedure
	- Open the Shop Floor Workbench window. If Reporting Mode 
	has been set to Employee Reporting on the used site an employee or 
	team must have been entered in the Enter As dialog box.
- Click Refresh. The operations will be displayed according to the 
	filter that is being used.
- Select the operation lines for which you wish to 
	start setup, and click Start Setup.
- The  
	Start Setup dialog box will be 
	opened. Based on the data entered in the  
	Shop Order window, 
	Machine Time and Labor Time options will be selected. You 
	can change the values if you want to. 
- Choose the resource which on the operation will be set up in the 
	Resource list.
- If run in Employee Reporting mode, enter the employees that will 
	work with the operation in the Employee table. If a team is entered in 
	Shop Floor Workbench, the employees currently in the team is displayed and may not 
	be changed. If run in Anonymous 
	mode, enter the crew size manually.
- Click OK. The start time can be viewed in the Clockings 
	tab.
- Click the Start Setup. The start time can 
	be viewed in the  
	Clockings tab.
 
To perform this activity from Time Clock
	- Click the Start Setup button in Time 
	Clock.
- Enter the Employee ID or the Team.
- Enter the Operation ID you want to start 
	setup for.
- If machine setup time exists for the operation, 
	Machine Time will be automatically set to Yes. Set it to No 
	if you do not want to start machine setup.
- Choose the resource on which the operation will be set up in the 
	Resource ID.
- If the existing clockings for the employee should 
	be stopped, select Yes in Stop Emp Clockings. The default 
	value is set based on the value of Allow Concurrent Operations for 
	the employee in Manufacturing Labor Class/Employee tab.
- Click OK.