Stop Production
Explanation
This activity is used to stop a started production on one or several 
operations.
When calculating operation hours, the priority of calculating the operation 
hours should be as follows:
	- Based on the calendar settings defined in the Manufacturing Labor 
	Class/Employees tab.
- If calendar is not defined, when IFS/Human Resources is installed, refer 
	the employee's work schedules defined in the Employee Schedules and 
	Rules window. 
- If employee’s schedule is day type independent or 
 If IFS/Human Resources is not installed, and no valid schedule exists for 
	the employee;
 then use the labor class calendar defined in the Basic Data for 
	Manufacturing Labor window.
This activity contains a Security Checkpoint which can be activated by an 
administrator. With an activated security checkpoint on a function you will have 
to authenticate yourself again in order to fulfill the function. Additionally, 
whenever a security checkpoint is successfully passed a security checkpoint log 
is written, creating an audit trail of what is done.
Prerequisites
The production (runtime) must have started on the operation.
System Effects
	- The started production will be stopped for the selected operation and 
	all operations with the same clocking sequence.
- The stop time will be recorded on the clockings. The clockings can be 
	viewed in the Clockings tab.  
- The cogwheel symbol the operation had during the production will be now 
	removed.
- The started production will be stopped. The 
	selected operation and all operations with the same clocking sequence will 
	be stopped.
- If Stop Reason is set to Interrupted an exclamation mark 
	will appear to the left in the operation list. 
- The status of the operation is set to either Partially Reported 
	or Interrupted depending on the selected Stop Reason.
- Transactions are created in operations history:
 The total time is calculated and one transaction per clocking and operation 
	is created in operation history.
 Time is calculated as: Stop time – Start time; calendar consideration
 
 For Machine Time the work center calendar is used
 
 For Labor Time the labor class calendar is used. If the employee has 
	a calendar connected this will override the labor class calendar for the 
	labor time.
 
 Depending on the site settings either all time, only calendar time or 
	calendar and overtime is included.
 
 In Anonymous Reporting mode, the crew size defined in the start 
	dialog will be saved on the labor transaction and used in the cost 
	calculation.
 
 In Employee Reporting mode, one transaction per employee is created and the 
	crew size is calculated with regards to other overlapping clockings for the 
	employee.
 
 The total time on the operations started at the same time (with the same 
	clocking sequence) will be proportionally divided among the operations 
	according to the planned time defined on the shop order operation line.
 
 Example: three operations have 10, 15, and 22 planned minutes (planned total 
	of 47 minutes), and in total 62 actual minutes are reported.
 
 10/47x62=13,1915
 15/47x62=19,7872
 22/47x62=29,0213
 13,1915 + 19,7872 + 29,0213 = 62
Window
Shop Floor Workbench
Time Clock
Related Window Descriptions
Shop Floor Workbench
Stop Production
Approve Operation
Time Clock
Procedure
To perform this activity from Shop Floor Workbench using 
Stop Production:
	- In the Shop Floor Workbench window, select 
	the operation line and click Stop Production.
- The Stop Production dialog box will open.
- Select an appropriate option in the Stop Reason list.
- Click OK. The finish time can be viewed in the Clockings 
	tab. 
To perform this activity from Shop Floor Workbench using 
Approve Operation:
	- In the Shop Floor Workbench window, select 
	the operation line and click Approve Operation.
- The Approve Operation dialog box will open.
- Select the Stop Clockings check box.
- Click OK. The finish time can be viewed in the Clockings 
	tab. 
To perform this activity from Time Clock:
	- Click the Stop Production button in Time 
	Clock.
- Enter the Employee ID or the Team.
- Operation IDs with ongoing clocking for operation 
	run by the employee 
	or the team will be listed, select the operation ID you want to stop 
	production 
	for.
- If you want to stop the machine clocking 
	also, select Yes in Machine Time.
- If you want to report an interruption, select an 
	interruption cause. Otherwise leave the field empty.
- If you want to close the operation select Yes 
	in Close Operation.
- Click Ok.