Calculate Project MS Level 1
Explanation
This activity is used to perform project master 
scheduling (project MS) for either a single part, or for all the parts belonging 
to a specific site and project planned netting group (PNG). This process uses 
information from the forecasted demand that you have entered and the actual 
backlog of orders. It calculates forecasted demand and actual orders, traces 
orders, and provides action messages. When initiating a project MS process for a 
site or PNG you may set it up so that project material requirements planning 
(project MRP) and material requirements planning (MRP) are run immediately after 
project MS.
Prerequisites
	- A project MS part needs to be defined.
- Forecasted demands need to be registered.
System Effects
	- If you perform project MS for a site or PNG, one 
	or more background jobs will be executed to perform project MS and, 
	optionally, project MRP and/or MRP.
- The project MS process generates proposals as 
	required. Shop order requisitions and purchase requisitions may also be 
	created for fixed proposals, if you have indicated that requisitions need to 
	be created. During the process, existing proposals and requisitions in the
	Planned status for the part are removed and new ones will be created 
	if necessary. These proposals are created for the forecast activities.
- Material transfer requisitions may also be created 
	to transfer material between activities.
- Action messages may be displayed in the MS level 1 Part/Action Messages 
	tab or in the MS Action Proposals 
	window. 
- The gross demand per activity is made available 
	and this forms the basis for the MRP calculation.
- The projected quantity of the part on-hand is 
	analyzed and displayed in the Projected Balance field in the MS Level 1 Part/Register Forecast 
	tab. The physical quantity on-hand is also updated. This value is used to 
	calculate the development of quantity on-hand and the quantity available to 
	promise.
Window
Calculate Project MS Level 1
Related Window Descriptions
Calculate Project 
MS Level 1
Procedure
	- Open the Calculate Project MS 
	Level 1 
	dialog box. 
- In the Site field, enter the short code of 
	the site for which you want to perform project MS, or select it from the 
	List of Values. If you enter % project MS will consider all your sites 
	during the calculation.
- In the Project PNG field, enter the ID of the 
	desired project PNG. If you enter % project MS will consider all the project PNGs that exist 
	in the selected site(s).
- In the Run Date field, enter the date when 
	you want to perform the calculation.
- Select the Stop Project MS on Error check 
	box if you want the project MS process to stop when errors are encountered.
- Select the Start PMRP Once Project MS Completes check box if you want PMRP to be performed after project MS.
- Select the Start MRP Once MS Completes check box if you want MRP to be performed after project MS.
- Click OK.