Define RRP Resources
Explanation
Use this activity to change the resource capacity information automatically 
entered when you enter a work center. You also can add new resources to the work 
center.
Prerequisites
This activity requires that the work center has been registered. 
System Effects
As a result of this activity, the system takes the specified quantity and/or 
efficiency into consideration when planning how much can be manufactured per day 
in the resource.
Window
Work Center
Related Window Descriptions
Work Center
Work Center/RRP Capacity
Procedure
Changing the quantity or efficiency: 
  - From the Work Center 
	list, select the work center for which you want to change the information.
- Open the 
	RRP Capacity tab.
- In the Units per Day and RRP Efficiency fields, change the 
	quantity that can be manufactured per day and/or efficiency.
- Save.
Add new resource: 
  - From the Work Center 
	list, select the work center for which you want to change the information.
- Open the 
	RRP Capacity tab.
- Create a new record in the table.
- Enter an identification of the resource and a corresponding description.
- Repeat steps 3-4 for every resource you want to register.
- Save.