Define RRP Unique Work Centers
Explanation
Use this activity to enter work centers to be used solely by resource 
requirements planning (RRP). The work centers you use as planning resources can 
have only the Planned  state in the work center register. Such work 
centers are usable only in resource planning. You can, however, also work with 
work centers that have the Active  state. This allows you to check 
workload in a bottleneck, for example.
The information you enter for RRP-unique work centers is used when you work 
with resource requirements planning. The information you enter for a work center 
is default when you work with the work center. The information you enter in the 
RRP Capacity
tab is used if the work center is a planning resource. The work center 
does not need to have a state of Planned for you to enter 
information here.
Prerequisites
There are no prerequisites for this activity.
System Effects
As a result of this activity, the system creates a work center solely used by 
RRP, if the State is Planned.
Window
Work Center
Related Window Descriptions
Work Center
Work Center/RRP Capacity 
Procedure
  - Create a new record.
- Enter the short code of the work center in the
	Work Center  
	field. This code can 
	consist of up to 5 alphanumeric characters. Enter a description for the work 
	center.
- In the Site field, specify the site at which the work center is to 
	be used. Use 
	the List of Values to select from 
	available sites.
- Specify the work center's queue time.
- In the Work Center Code  
	field, specify whether the work center 
	is internal or external.
- In the Calendar ID field, enter the calendar to use. Use 
	the List of Values to select from 
	available calendars.
- Specify the utilization of the work center in the Utilization 
	field. The default value is 100.
- Specify the work center's unit of measure. This must be Hour if the 
	work center is Active. If the work center is Planned, you can use any unit 
	of measure in the system. Use 
	the List of Values to select from 
	available units of measure.
- 
  
  In the State field, specify whether the work center is an active or a planning 
	resource. To register an RRP-unique work center, select Planned.
- Save.