Manually Update Level 1 Master Schedule 
Explanation
This activity is used to manually update master schedule receipts for the level 1
master schedule. Plan Period Templates are used to display master schedule
quantities in a series of date periods. Only a fixed number of periods, the
first 40, will be displayed.  A period template with a past due period
cannot be used in master scheduling for multiple parts. If a period template
with a past due period is selected, then a message will appear before
attempting to query. The Period Template range and MS Set should be selected to group MS Level 1 data. 
In the MS for Multiple Parts window, only Level 1
Updated rows can be updated. The value in each period represents a sum of master
schedule receipts that is generated on every workday within the periods. When
you save the changes, the new value will be evenly distributed  to each workday in the
period.
The re-calculation of the current template details may be necessary if the current
date does not match the begin date of the selected period range. 
Prerequisites
  - This activity requires the existence of a Level 1 part that has an associated
set of planned customer demands. 
-  Master schedule level 1 parts must have been
entered and the forecasts registered. 
-  Master schedule calculation of level 1 must
have been performed. 
- To update the available forecast and available
    actual values, at least one Level 1
Updated row that has been modified and not saved is required. 
System Effects
Window
MS Level 1 Part
Related Window Descriptions
MS for Multiple Parts
MS Level 1 Part
Select
Period Template
Procedure
  - Open the MS for Multiple Parts window, and
    populate it.
- Right-click and then click  Select Period
    Template. Select MS set
    and the period range in the Select Period Template dialog box.
- After updating one or more values of the Level 1 Updated
    quantity type in one or more
    rows, save the changes (F12).
- The level 1 forecast line will be updated with the new, calculated,
    master schedule receipt value.
- The system will recalculate the available forecast and
    available actual values.
- The results can be queried for in the 
	MS Level 
	1 Part window.
- If you want to recalculate the current template details, right-click and
    then click
    
    Recalculate Period Template. The 
	Recalculate Period Template
    dialog box opens, with the current date displayed in the Period 1 Begin
    Date field.
- If necessary update the begin date and the calendar ID to be
    used.
- Click  OK to recalculate the period template with the specified begin date
    and calendar ID.
- Right-click and then click Run MS Level1 to
    calculate the master schedule level 1.
- The 
	Calculate MS Level1
    dialog box opens. The value in the Run Date  field will be used as default
    for the start
    date of the first period. Select the MS set for which
    master scheduling will be run, and click OK.