Evaluate MS Result using Detailed Graph 
Explanation
Use this window to generate a graph that shows Master Scheduling
data for a selected Level 0 or Level 1 part belonging to a specified site. The types of
data shown are forecast, supply, demand, projected balance and projected time phased safety stock. You can also generate
overlay graphs that show cumulative unconsumed supply or cumulative unconsumed forecasts. 
Prerequisites
This activity requires that a Level 0 or Level 1 part exists. A
period template also must exist.  
System Effects
As a result of this activity, the system generates a graph
of Master Scheduling data for a user-specified Level 0 or Level 1 part. The graph includes
forecast, supply, demand, and projected balance data and projected time phased safety stock. The system also generates overlay
graphs showing cumulative unconsumed supply or cumulative unconsumed forecasts. The graph
appears at the bottom of the Detailed MS 
Graphic window.
Window
Detailed MS Graphic
Related Window Descriptions
Detailed MS Graphic
Recalculate
Period Details
MS Graph Parameters
Procedure
  - Open the 
	Detailed MS Graphic window.
- To generate graphical data for a Level 0 part instead of the default Level 1, click 
	Zero in the Level area. 
- Populate the Detailed MS Graphic 
	window. Alternatively, search for a part in the Part No field, along 
	with relevant site. If using a project master scheduled part, search for the 
	part with the relevant PNG. 
- Right-click and then click Show Graph. The 
	MS Graph Parameters
    dialog box is opened. If you receive an error message after clicking OK in this dialog box, go to step 5 below.
- Make the following choices the 
	MS Graph Parameters
    dialog box:
      - In the Period area, check the default period
        range displayed in the Period Begin Date and Period End Date 
		fields. To change this period
        range, type the number of the period that you want to use as the period begin number in
        the Begin No field. Then type the number of the period that you want to use as the
        period end number in the End No field. 
- In the Plot Forecast area, click Unconsumed to make the graph include non-cumulative unconsumed forecast 
		data. Alternatively, click Full to make it include the entire set of non-cumulative forecast data (consumed as well as unconsumed).
- In the Plot line for Cumulative area, click Unconsumed Forecast to make the graph include cumulative unconsumed forecast data.
        Alternatively, click Unconsumed Supply to make it include
        cumulative unconsumed supply data.
 
- Click OK. The system now generates a detailed MS
    graph for your specified period range and type of data.
- If you receive an error message indicating that the period
    template date does not match the part's last run date, right-click and then 
	click Recalculate Period Template. Click OK to recalculate the template with the
    correct begin date. Then right-click and click Show Graph again. When the 
	MS
    Graph Parameters dialog box appears, follow steps 4 and 5 above.