Connect PM Action 
Explanation
Use this activity to link Separate PM Actions into structures. You can do that by
selecting a superior PM Action, and then connecting underlying PM Actions. PM structures
are useful when a job involves several maintenance organizations and you want a work order created for
each maintenance organization.
Prerequisites
  - The separate PM action to be connected must have been entered in IFS/Preventive and
    Corrective Maintenance. 
- The PM action to be connected should not be in any replacement
    structure,  i.e., it should not be a PM action which replaces other PM
    actions or gets replaced by some
    other PM action.
- The PM action to be connected should have a valid revision in either the
	Preliminary or Active status. 
System Effects
As a result of this activity, a Separate PM Action is included in a structure. 
The following effects can also be observed depending on the information 
specified in the superior PM:
	- When a PM structure is created with or without Calendar generation 
	details defined in the superior PM, the calendar details defined in the 
	underlying PMs will be replaced with the corresponding details from the 
	superior PM. 
- When a PM structure is created with or without Event generation details 
	defined in the superior PM, the event details defined in the underlying PMs 
	will be replaced with the corresponding details from the superior PM.
- When a PM structure is created with or without Criteria generation 
	details defined in the superior PM, the same or different criteria details 
	defined in the underlying PMs will be removed. Once criteria on the superior 
	PM is satisfied and Condition Generation is performed, Work Orders will be 
	generated for all PMs of the structure. Further a Work Order Structure will be 
	created.
Window
Separate PM Action
Related Window Descriptions
Connections for Separate PM Action
Procedure
  - Open the  Separate PM Action window and query for an
    existing PM Action.
- Right-click and click Connections. The 
	Connections for Separate PM Action
    window appears.
- Create a new record (F5).
- In the  Connected PM No field, use the List of Values to select a PM
    Action. 
- In the Revision field, use the List of Values
    to change the revision of the selected PM action if necessary.  
- Save the information (F12).