Manually Generate Work Order
Explanation
Use this activity to manually generate work orders directly
from PM actions. You can do that if you need to
generate a work order for a certain PM action,
regardless of generation conditions. If you want to have several progressing WO 
at the same time or generate any line, then you need to set the Performed 
Value Based and Performed Date Based to No.
Prerequisites
The Separate PM action should be active and valid. 
System Effects
As a result of this activity, the current PM action will
generate a work order. It will then be available for further preparations along with other regular work orders.
Window
Separate PM Action
Related Window Descriptions
Separate PM Action
Procedure
  - Open the  Separate PM Action window and query for an existing record (F3).
- Right-click any where on the window and click Generate Work Order. 
- If you want to manually generate a work 
	order from a calendar plan or condition plan click the Maintenance Plan tab for 
	the PM action, 
	select the required line, right-click and click Generate Work Order.
- If Performed Date Based is Yes then it is only allowed to 
	manually generate next due calendar line and if Performed Value Based 
	is Yes, then it is only allowed to manually generate next due condition 
	line with a generation value.