Set PM Inventory Part Demand Horizon for PM Actions per 
Site
Explanation
This activity is used to define the PM Inventory Part Demand Horizon for a 
certain Site which will be used to determine if the inventory parts demand of an 
Active Preventive Maintenance Action occurrence/plan line defined on the same 
site will or will not be shown in the Inventory Part Availability Planning 
window when queried for an inventory part defined in the Preventive Maintenance 
Action.
Prerequisites
To perform this activity, the site must be defined.
System Effects
	- PM Inventory Part Demand Horizon creates the upper limit with the 
	deviation from the current system date and all Active Preventive Maintenance 
	plan lines with the planned start lying in between the system date and the 
	upper limit will be shown in the Inventory Part Availability Planning 
	window when queried for an inventory part defined in the PM Actions Material 
	tabs.
- Depending on the inventory part, these Maintenance plans lines will be shown 
	as demands with the Type as 'PM Action'.
- If the value of PM Inventory Part Demand Horizon is NULL, it will 
	consider the PM_PLAN_HORIZON and demands will be available up to that 
	value. If it's '0' no demands will be available.     
Window
Site 
Related Window Descriptions
Site
Site/Extended Site Info 
Site/Maintenance 
Procedure
	- Open the Site 
	window.
- Populate (F2) or query (F3) for the necessary site.
- Click the Maintenance tab..
- Set/Change the value in PM Material Demand Horizon field in days.
- Save the information (F12).
Note: When creating a new Site and upon saving the Extended Site Info 
by default PM Inventory Part Demand Horizon will be set to '0'.