Define
Production Line Operating Parameters
Explanation
This activity is used to enter production line operating parameters, which
are needed for production line
management. The parameters are as follows:
  - Daily Operating Minutes:This figure is used as the input for takt time
    calculations. You can enter this value manually, or retrieve the average
    daily run minutes from the production line calendar, for a sample date range.
- Default Schedule Horizon:
    
    This is used as the basis for calculating default schedule date ranges when
    retrieving demands or calculating proposed schedules. The Firm and Schedule
    horizons are used to calculate a date range to be used in the features.
- Default Scheduling Method: This
    is the default method that will be used when running the scheduling feature or when
    the schedules
    are loaded directly from the customer order demands. You
    should select one of scheduling logics to be used when loading the line.
    The available options are: 
    
      - Schedule to exactly meet
        demand.
-  Backward
        schedule using line rate as capacity limit.
- Forward schedule using line
        rate as capacity limit.
 
Prerequisites
  - 
    A production
    line must have been created.
- 
    A schedule horizon must
    have been defined. 
System Effects
  - Operating minutes will be used only for the takt time
calculation as an input, but will be stored with the production line.
- The default schedule horizon will be used as the basis for
    the default date range
calculations when retrieving the line demand, generating proposed schedules, or
copying proposed schedules to the actual schedule. If a default schedule
horizon is not defined, the date ranges must be entered manually in each of the activities. 
    
 
Window
Production Line
Management
Related Window Descriptions
Production Line Management
Procedure
  - Open the 
	Production Line Management  window.
- Right-click and then click Calculate Operation Minutes from the Calendar. Otherwise,
    you can manually enter the daily operating minutes.
- Enter the horizon ID in the  Default 
    Scheduling Horizon field, or select it from the List of Values.
- Select the default scheduling method from the drop down list of Production
    Schedule Load Methods.