This activity is used to process material transfer
requisitions (MTR). MTR is an object that handles part transfer between project activities. When you 
execute MTR, parts will be transferred from the issuing  PPSA to the receiving 
PPSA. Along with the part, its cost will also be transferred. To perform this 
activity, you must have access to the site. (A PPSA refers to program ID, 
project ID, sub project ID, activity ID).
Note: If you have selected the Automatic MTR check 
box in the 
Planned Netting Group window, then MTR with the Inventory
supply source type will be 
automatically executed by multi project requirements planning (MPMRP).
When you create MTR manually, the MTR 
Manually Created check box in the 
Material Transfer Requisition
window will be automatically selected. 
If the inventory location in the from activity or receiving activity is frozen 
for transactions, automatic MTR process will be stopped at the Planned 
status. A record will be created in the Material Transfer Requisition 
/Logs tab. 
It is possible to generate MTR for planning purpose only by selecting 
Generate MTR for Planning Only check box in the 
Planned Netting Group 
window. By using this MTR, parts are planned across project activities but will 
not be transferred. Thus the cost will also not be transferred. However If the 
activities belong to different projects, then cost will be transferred.
If Allowed Manual is selected in the Within PNG 
Transfer list or the Between PNG Transfer list in the 
Planned Netting Group 
window, each planner in the issuing PPSA and the receiving PPSA need to approve the MTR 
before it is executed. 
The Excluded check box will be 
selected to indicate the Material Transfer Requisitions (MTR) which were 
excluded from the PMRP calculations. This will be valid for MTRs which are in 
the status Planned, Released or Partially Approved and with the supply type Inventory. 
 Prerequisites
	- The PMRP must have been performed without any 
	errors.
- The project activities (PPSAs) in the  From 
	area must be in Released state. The activities in the To area 
	need not be in Released state, but the project to which they belong 
	must have been approved.
- The issuing
      PPSA and the receiving PPSA must have been connected 
	in the 
	Planned Netting Group window.
System Effects
	- The part and cost will be transferred from the issuing
      PPSA 
	to the receiving PPSA.
- The quantity on hand and inventory cost on the 
	receiving PPSA will be increased.
Window
Material Transfer 
Requisition 
Related Window Descriptions
Material Transfer Requisition
Material Transfer 
Requisition/Detail 
Material Transfer 
Requisition/Paybacks
Material Transfer 
Requisition/Logs
Procedure
	- Open the 
	Material Transfer Requisition 
	window.
- To create an MTR manually, create a new record and enter the part number
      you want to transfer or select a value from the List of Values.
- Based on 
	the values you have specified in the Borrow/Payback field in the
      
	Planned 
	Netting Group window, the value in the Transfer 
	Type field appears automatically. Only MTRs with the Transfer Type field 
	having the value Planning can be changed back to Planned 
	status.
- Select the 
	appropriate supply source. Possible values are Inventory, Order, and 
	Requisition. 
- Click the 
	Detail tab and enter the 
	short name of the PPSA that requires the part, or use the List of Values.
- In the  From group, enter the short name of 
	the PPSA from 
	which the part is transferred or borrowed or use the List of Values.
 Note: All the information related to PPSA will appear automatically.
- Save the record.
 Note:  Based on the values you have selected in the Within PNG Transfer and
      the Between PNG Transfer lists in the 
	Planned Netting Group window,
      the values in the Approval Type field will appear automatically. The possible values are Manual 
	and Automatic.
- To release the MTR
      , right click and then click Release. 
	The status will be changed to Released.
- To approve the issuing 
      PPSA and the receiving PPSA of both manually and automatically created 
	MTRs, 
	right-click and then click Giving Approval and Receiving Approval 
	respectively.
      
 Note: You can perform this only if you have selected Manual as 
	the approval type 
	in the corresponding group boxes. Executing Giving Approval will reserve any available 
	material when the Transfer Type is Transfer and the Supply Source is Inventory.
- When the planners from the issuing
      PPSA or the receiving PPSA approve the MTR, the user IDs will automatically
      appear in 
	the Approval field in the respective group boxes. The status will be 
	changed from Released to Approved. If only one of the planners from the 
	issuing  PPSA or receiving PPSA approves the MTR, the status will be set to 
	Partially 
	Approved.
- If you want to remove the approval, right-click 
	and then click Withdraw Approval. 
 Note: Executing Withdraw Approval will unreserve any material attached to it.
- If you do not want to re-plan MTR  in the next 
	MPMRP run, right-click and then click Refuse.
- To cancel creating an MTR , right-click and then click 
	Cancel.
 Note: Deleting a MTR or changing the status to Cancel or 
	Refuse will unreserve any material attached to it.
- To execute an MTR, right-click and then click Execute. 
	This option is available only if the MTR is in the Approved status.
	 
 
 Note:  If the supply source is Inventory, information related to the source inventory part will be stored in the
	Source
	Inventory Info table. This information must be entered by the user if the 
	MTR is manually created. For the MTRs created by MPMRP, this information will 
	be automatically entered by MPMRP.
 
 If the supply source type is Order or Requisition,
	information related to the source order 
	or requisition will be stored in the Source Order Info 
	table. This information must be entered by the user if the MTR is manually 
	created. Otherwise it will be entered by MPMRP.
 
 1. The Order Ref. 1 field represents the order number on the 
	Shop Order/Purchase Order 
    tab or the requisition number on the Shop 
	Proposal/Purchase   Requisition tab.
 2.The Order Ref. 2 field represents the release number on the  
	Shop Order  
	window or
	the line number of 
	Purchase Order/Purchase Requisition 
	tab.
 3.TheOrder Ref. 3 represents the sequence number on the  
	Shop Order  
	window or
	the release number on the Purchase Order/Purchase Requisition 
	tab. If the transfer type is 
	Borrow/Payback, the columns in the 
	Paybacks tab will be 
	filled
      automatically. It will contain the connected payback MTR information.
 All status changes of the MTR transactions will be recorded on the 
	Logs 
	tab.