Propagate Date Downstream
Explanation
This activity is used to propagate dates downstream in a DOP
structure. The dates on higher levels in the DOP structure change with respect to the due
date on the DOP Order on which you perform the command and the lead time offset.
Prerequisites
This activity requires that the parent DOP Order has not reached
the Released state. 
System Effects
As a result of this activity:
	- The revised due and start dates on
higher levels in the DOP structure are changed based on the revised due date of the DOP 
	Order, the lead time offset of the DOP Order, and the lead time of the parent DOP 
	Order
part.
- The lead-time is calculated due to the lot size and the routing revision and
alternative for the parent DOP Order. The Due Date in the
	Demand area on the
	
	DOP Header/Detail tab is the same as the revised due date on the
top DOP Order.
Window
DOP Header
DOP Order
Related Window Descriptions
DOP Header
DOP Header/Structure
DOP Header/Tree Structure
DOP Order
DOP Order/Detail
DOP Order/Tree Structure
Procedure
  - Select the DOP Order from which to start a downstream propagation
    of dates.
- Right-click and point to
	Propagate Date/Quantity, then click
	
	Propagate Date Downstream.
From the graphical object structure (DOP Order/Tree Structure or 
DOP
Header/DOP Structure): 
  - Select the DOP Order from which to start a downstream propagation of
    dates.
- Right-click on the selected DOP Order object, point to Propagate 
	Date/Quantity and then click 
	Propagate Date Downstream.