Run Project MRP for Components 
Explanation
This activity is used to run project MRP for project 
planned master scheduled parts to plan its nonstandard planned component 
supplies.
Prerequisites
To perform this activity, a master schedule part has to 
be created which is connected to a project and master scheduling has to be 
performed for the part.
System Effects
As a result of this activity, selective project MRP 
will be performed and supplies will be planned for the components of the master 
scheduled part.
Window
MS Level 1 Part
Related Window Descriptions
MS Level 1 Part
Run Project MRP for Components
Procedure
	- Open the MS Level 1 Part 
	window.
- Query for the record. 
- Right-click and click Run Project MRP for 
	Components. (This right mouse button option will 
	only be enabled for project master scheduled parts.)
- The Run Project MRP for Components 
	dialog box will be opened with part number and site already selected.
- Select the date on which you want the project MRP 
	to be executed. The current date is used by default.
- If you want to stop the project MRP process when 
	an error occurs, you can select the Stop PMRP on Error check box.
- To add one day leadtime back-off to planned 
	receipts, select the Add 1 Day Lead Time check box.
- To generate project MRP action messages for 
	dependent demands of phantom parts, click the Phantom Part Dependent Demand 
	Message check box.
- To start the MRP process immediately after the 
	Project MRP process is finished, click the Start MRP Process Once PMRP is 
	Completed check box  
- If you want the project MRP process to create 
	safety stock replenishment orders on the MRP run date, select the Plan 
	Safety Stock Receipt on PMRP Run Date check box. If it is not selected, 
	safety stock replenishment orders will be created on the event date itself.
- If the Run Integrated with CRP check box is 
	selected, CRP backward scheduling logic will be used to schedule shop order 
	requisitions.