Study MRP Part Information
Explanation
This activity is used to study information about an inventory part which was planned by 
material requirement planning (MRP) or project material requirement planning (project MRP). 
  - Expected receipts and deliveries of the part
- Existing material/gross requirements
- Planned and proposed receipts from MRP and project MRP
- Material transfer requisitions (MTR) created by multiproject material 
	requirements planning multiproject MRP)
- Gross requirements for the part calculated by MRP and project MRP (the requirements when MRP or 
	project MRP 
	considers only receipts and deliveries, not the quantity on hand)
- Material transfer requisitions (MTR) in the Planned, Released, or Partially Approved 
	statuses and which do not have a valid source to supply. 
  The Exclude check box will be selected to indicate these records were excluded from the 
	project MRP calculation. This will be valid for MTRs 
	with the Inventory supply type
- The shop order or production schedule (MRP only) that generated the demand; if the part is a component, the parent part is displayed
Prerequisites
- The selected inventory part should be set to be planned by MRP or project MRP by performing 
site MRP, network MRP, selective MRP or performing project MRP for activity, project or 
planning netting groups.
- Even though parts that are set to be planned by IFS/Master Scheduling or project 
master scheduling are 
not displayed, if you need to plan the actual demand of those parts by MRP or 
project MRP, 
then it is required to select the Create S/P from MRP value for the Create S/P Req 
option in the MS Level 1 Part or Project MS Part 
window and run MRP or project MRP after that.
System Effects
N/A
Window
MRP Part Information 
Related Window Descriptions
MRP Part Information
MRP Part Information/Details
MRP Part Information/Receipts and Deliveries
MRP Part Information/Gross Requirements
MRP Part 
Information/Bottom up Planning
MRP Part Information/Gross Requirements by Template
MRP Part Information/Action Proposals
MRP Part Information/Pegged Supply
MRP Part Information/Created MTRs
Multilevel Structures 
Material Plan Multi-Site
Material Plan Graph
Inventory Part Availability 
Planning
Select Period Template 
Procedure
  - Open the MRP Part Information
	window.
- Search for the part for which you want to study the specified 
	information. 
- Click the Details tab to view detailed information
    regarding the selected part.
- Click the 
	Receipts and Deliveries tab to view expected
    receipts and deliveries.
- Click the 
	Gross Requirements 
	tab to view gross
    requirements for the part calculated by MRP or project MRP.  The icon showing 
	the component in the navigator will indicate whether the part is planned 
	using MRP, project MRP or any other planning method.    
- Expand the part structure tree view and click on a desired part to move between different structure items.
- Right-click in the header and then click the relevant option to open the Material Plan Multi-Site, 
	Inventory Part Availability Planning, 
	and Material Plan Graph 
	windows. 
- Right-click on any part in the part structure and select Populate this part in Master. This will populate the selected child part in current 
	MRP Part Information
	window. To navigate back to the previously viewed part, right click and 
	select Populate Original on the header.
- Right-click on a part and select Negative Projected On Hand, 
	Late Order Components, Early Order Components, or Remove Order 
	Components to mark alerts based on apparent material supply problems 
	detected by the most recent MRP run. 
-  Click the Gross Requirements tab to 
	study the gross demand for the part calculated by MRP. Select a row, 
	right-click and click Supply/Demand details for more information. 
- Click the Bottom up Planning tab to view 
	the downstream items which use the parts in the header. Repeat steps 6-9 to 
	execute similar action on bottom up planning part navigator. 
- Click the Gross Requirement By Template tab to view the gross requirement for the part 
	according to the given template 
	Select a row, right-click and select Recalculate Period Template to recalculate the template with 
	a different template start date and desired calendar to view the gross requirement according to that recalculated template.
- Click the Action Proposals tab to view MRP or 
	project MRP action messages generated for the part. You can perform follow up actions using the right-click options available in action messages.
- The Pegged Supply 
	tab will be enabled only if the part is project MRP planned. 
	Click this tab to study pegged supplies for the part within the selected activity. Supplies such as 
	inventory, open order, or MRP receipt are pegged to demands.
- The Created MTR tab will be 
	enabled only if the part is project MRP planned. During multiproject MRP, material 
	transfer requisitions (MTR) are generated to transfer parts between activities (if needed). This tab is used to study all the MTRs created for the part and activity.
	
 Note: To open the 
	Multilevel Structures
	window, right-click in the header and then click Part Structure.
 To change period template, right-click and click the Select Period Template option.